Question

Problem (2) (12) For the concrete dam and soil profile shown in the Figure below, the flow net is cons channel and 8 isted of 3 fNow rops, calculate: a) The rate of seepage under the dam in ft /sec/ft. b) Pore water pressure at points A, C, and D in Ib/ft. c) The uplift force in lb/ft at the base of the dam due to water pressure C use points C and D). 20
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ven ay nd Ab 5 Conside down gaam totes level, datum Total head ot ubsltam Cath Head IST Tal, head at c = 20-ls.xl; ls.1asft E. Total head at A=a-Las-9.375 Elevatron head at A - = 9.375-(-21 = | 30.375 ft Eleudim head atD: -5-52-loft 6.1tr-(-10) = 16-6.81S x 62- dam s hoon belew 43壮 (1755 +1a53) x 43 | 60372 lb/ft

Add a comment
Know the answer?
Add Answer to:
Problem (2) (12) For the concrete dam and soil profile shown in the Figure below, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Complete the following for the impermeable dam shown below: a. Identify a datum, indicate the...

    2. Complete the following for the impermeable dam shown below: a. Identify a datum, indicate the first and last equipotential lines, and indicate the first and last flow lines b. Draw the flow net and determine the seepage under the dam. Calculate the pore water pressure (u) at points A, B, and C (in units of kPa). d. c. Estimate the uplift force (Fu) under the concrete dam (in units of kN/m of length) Note: an additional figure is included...

  • *need the uplift force Problem 5 Consider the flow net shown below. The sandy soil has...

    *need the uplift force Problem 5 Consider the flow net shown below. The sandy soil has an average saturated unit weight of 20 kN/m and permeability of 0.002 cm/s. Numbers provided are elevations from the interface with the impervious layer. The other "set" of numbers counts the number of head drops. (a) Compute the distribution of pore water pressure acting along the base of the concrete weir, and determine the vertical uplift force that the water pressure exerts on the...

  • (1) The flow net with approximate square cells for a concrete dam is shown. The silt...

    (1) The flow net with approximate square cells for a concrete dam is shown. The silt has a hydraulic conductivity of 0.2 ft hr. (a) What is the approximately seepage rate (ft/hr/ft)? (b) What are the total head (hr), elevation head (he), and pressure head (h) at points A and B h e (ft) he (ft) hrift) Point A (2) The flow net with approximate square cells for a single sheet pile is shown as below. The hydraulic conductivity of...

  • Draw a flow netlfor the case of a long concrete dam shown in the Figure below...

    Draw a flow netlfor the case of a long concrete dam shown in the Figure below and calculate the quantity of seepage underneath the dam. The soil underneath the dam is homogeneous and isotropic with a coefficient of permeability of 1.8 x 106 m/s. Determine the minimum weight of the dam required to maintain a factor of safety of 1.5 against the uplift of the dam. If the saturated unit weight of the soil is 18 KN/mP, check whether quicksand...

  • 50 m Impermeable Concrete dam 6 m 1 m 10 m PtA (at mid-point of layer...

    50 m Impermeable Concrete dam 6 m 1 m 10 m PtA (at mid-point of layer and centre of base) DATUM Impermeable bedrock Figure 2: Concrete dam (not to scale) Figure 2 shows the cross-section through a long concrete dam in anisotropic soil. The horizontal and vertical permeability of the soil are: K 25 x 10-4 cm/sec and Ky 1 x 10-cm/sec.. (a) Calculate the transform parameter a. In your exam booklet, draw the transformed flow domain to scale and...

  • 3. The flow net shown below illustrates flow conditions beneath a concrete dam featuring an upstream...

    3. The flow net shown below illustrates flow conditions beneath a concrete dam featuring an upstream "clay blanket" (an impermeable clay layer) and a downstream "cutoff wall", both of which serve to lengthen the flow path. The coefficient of permeability, k, of the permeable strata is 8 x 10 cm/s. a. Calculate the flow rate, q, per day beneath the dam (per m of dam out-of-plane). b. Calculate the total head, elevation head, pressure head, and pore water pressure at...

  • Problem 13 a. Draw the flow net for the dam shown below (datum is at the...

    Problem 13 a. Draw the flow net for the dam shown below (datum is at the 54 ft bedrock-soil interface). The dam has a 36-ft sheet pile driven into the granular soil layer. Redraw the schematic to scale. Use solid 24 ft 21 ft lines to indicate flow lines and dashed lines to indicate Soil equipotential lines. b. Calculate the rate of seepage at 36 ft the exit of the dam in ft/day per 60 ft Sheet pile unit width...

  • The following figure shows an earthen dam with a reservoir depth of 60 feet. Undermeath the...

    The following figure shows an earthen dam with a reservoir depth of 60 feet. Undermeath the dam is a 50-foot thick uniform pervious soil layer that is underlain by impervious soil. Water flows through and beneath the dam and drains into a filter and drain system. The embankment material and underlying soil both have a hydraulic conductivity (k) of 1X10 cm/sec. 2. a. Compute the seepage through the dam (per foot of dam) in f'/day. (Note: 1 foot 30.48 cm,...

  • Problem 1 Ground Surface A soil profile is shown to the right. The groundwater table is...

    Problem 1 Ground Surface A soil profile is shown to the right. The groundwater table is located 15 feet below ground. Calculate the total stress, pore water pressure and effective stress in the vertical and horizontal direction at points a, b, and c located Coarse Sand -120 lb/ft Ko 0.4 %at: 125 lb/ft3 a) 15, b) 40, and c) 58 feet below the ground surface. Stiff Clay = 110 lb/ft3 %at 115 lb/ft3 Ko= 1.3 58 Limestone Bedrock

  • 1- A long coffer dam is to be constructed to hold water as shown in the figure. The geometry of t...

    1- A long coffer dam is to be constructed to hold water as shown in the figure. The geometry of the final wall is given. The total unit weight of the soil is 20kN/m . Draw the flow net for the steady state seepage flow which occurs under this wall. From the flow net determine: a) The height above point A to which water would rise in a piesometer tube. b) The flow under the wall per metre run of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT