Direct Labor Variances
Alpine Bicycle Company manufactures road bikes. The following data for September of the current year are available:
Quantity of direct labor used | 480 hrs. |
Actual rate for direct labor | $10.5 per hr. |
Bicycles completed in September | 230 |
Standard direct labor per bicycle | 2 hrs. |
Standard rate for direct labor | $10.7 per hr. |
a. Determine the direct labor rate variance and direct labor time variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Rate variance | $ | |
Time variance | $ | |
Total direct labor cost variance | $ |
b.
How much direct labor should be debited to Work in Process?
$______
Rate Variance = (SR-AR) * AH
= (10.7-10.5) * 480
= - 96 Favourable (minus sign)
Time variance = (SH - AH) *SR
= (2*230 - 480) * 10. 7
= 214 Unfavorable
Total Cost variance = 96F+214U
= 118 Unfavorable
B.
Direct labor debited to wip
= (230*2*10.7)
= 4922
Comment if you face any issues
Direct Labor Variances Alpine Bicycle Company manufactures road bikes. The following data for September of the...
Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 640 hrs. Actual rate for direct labor $13.7 per hr. Bicycles completed in April 300 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $14 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...
Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $10.6 per hr. Bicycles completed in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $10.8 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...
Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are available: 5,000 hrs. Quantity of direct labor used Actual rate for direct labor $22.75 per hr. 800 bicycles Bicycles completed in October Standard direct labor per bicycle 6.0 hrs. Standard rate for direct labor $24.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a...
Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $12.6 per hr. Bicycles completed in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $12.9 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...
Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 740 hrs. Actual rate for direct labor $12.7 per hr. 350 bicycles Bicycles completed in April Standard direct labor per bicycle Standard rate for direct labor 2 hrs. $13 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...
Direct Labor Variances La Batre Bicydle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 480 hrs. Actual rate for direct labor $11.7 per hr. Bicycles completed in April 230 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $11.9 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...
Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $12.70 per hr. Bicycles completed in October 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $13.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a...
Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: 610 hrs Quantity of direct labor ussed $14.4 per hr Actual rate for direct labor 290 bicycles Bicycles completed in April 2 hrs Standard direct labor per bicycle Standard rate for direct labor $14.7 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...
Direct Labor Variances La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 640 hrs. Actual rate for direct labor Bicycles completed in July $13.40 per hr. 300 bicycles 2 hrs. $13.70 per hr. Standard direct labor per bicycle Standard rate for direct labor a. Determine the direct labor rate variance, time variance, and total direct labor cost variance. Enter a favorable variance as a...
E13-24 Direct labor variances Death Valley Bicycle Company manufactures mountain bikes. The following data for Octo- ber of the current year are available: Quantity of direct labor used 1,100 hrs. Actual rate for direct labor $18.50 per hr. Bicycles completed in October 350 Standard direct labor per bicycle 3 hrs. Standard rate for direct labor $19.00 per hr. Planned bicycles for October 375 Determine the direct labor rate and time variances.