  1. Direct Labor Variances

    Alpine Bicycle Company manufactures road bikes. The following data for September of the current year are available:

    Quantity of direct labor used 480 hrs.
    Actual rate for direct labor $10.5 per hr.
    Bicycles completed in September 230
    Standard direct labor per bicycle 2 hrs.
    Standard rate for direct labor $10.7 per hr.

    a. Determine the direct labor rate variance and direct labor time variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

    Rate variance $
    Time variance $
    Total direct labor cost variance $

    b. How much direct labor should be debited to Work in Process?
    $______

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Rate Variance = (SR-AR) * AH

= (10.7-10.5) * 480

= - 96 Favourable (minus sign)

Time variance = (SH - AH) *SR

= (2*230 - 480) * 10. 7

= 214 Unfavorable

Total Cost variance = 96F+214U

= 118 Unfavorable

B.

Direct labor debited to wip

= (230*2*10.7)

= 4922

Comment if you face any issues

Add a comment
Know the answer?
Add Answer to:
Direct Labor Variances Alpine Bicycle Company manufactures road bikes. The following data for September of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 640 hrs. Actual rate for direct labor $13.7 per hr. Bicycles completed in April 300 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $14 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $10.6 per hr. Bicycles completed in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $10.8 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for...

    Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are available: 5,000 hrs. Quantity of direct labor used Actual rate for direct labor $22.75 per hr. 800 bicycles Bicycles completed in October Standard direct labor per bicycle 6.0 hrs. Standard rate for direct labor $24.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $12.6 per hr. Bicycles completed in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $12.9 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 740 hrs. Actual rate for direct labor $12.7 per hr. 350 bicycles Bicycles completed in April Standard direct labor per bicycle Standard rate for direct labor 2 hrs. $13 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Batre Bicydle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicydle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 480 hrs. Actual rate for direct labor $11.7 per hr. Bicycles completed in April 230 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $11.9 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for...

    Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available: Quantity of direct labor used 470 hrs. Actual rate for direct labor $12.70 per hr. Bicycles completed in October 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $13.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a...

  • Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

    Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: 610 hrs Quantity of direct labor ussed $14.4 per hr Actual rate for direct labor 290 bicycles Bicycles completed in April 2 hrs Standard direct labor per bicycle Standard rate for direct labor $14.7 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable...

  • Direct Labor Variances La Barte Company manufactures commuter bicycles from recycled materials. The following data for...

    Direct Labor Variances La Barte Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 640 hrs. Actual rate for direct labor Bicycles completed in July $13.40 per hr. 300 bicycles 2 hrs. $13.70 per hr. Standard direct labor per bicycle Standard rate for direct labor a. Determine the direct labor rate variance, time variance, and total direct labor cost variance. Enter a favorable variance as a...

  • E13-24 Direct labor variances Death Valley Bicycle Company manufactures mountain bikes. The following data for Octo-...

    E13-24 Direct labor variances Death Valley Bicycle Company manufactures mountain bikes. The following data for Octo- ber of the current year are available: Quantity of direct labor used 1,100 hrs. Actual rate for direct labor $18.50 per hr. Bicycles completed in October 350 Standard direct labor per bicycle 3 hrs. Standard rate for direct labor $19.00 per hr. Planned bicycles for October 375 Determine the direct labor rate and time variances.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT