The final packing operation requires 13 tasks. Sun River bottles their sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 3,000 bottles of this product.

TASK PERFORMANCE TIME (MINUTES) TASK MUST FOLLOW
1 0.1
2 0.1 1
3 0.1 2
4 0.2 2
5 0.1 2
6 0.2 3, 4, 5
7 0.1 1
8 0.1 7
9 0.2 8
10 0.1 9
11 0.2 6
12 0.2 10, 11
13 0.1 12


Using the above data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria. (Round your answer to the nearest whole percent.)


Efficiency of line balance at cycle time_______ %

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cycle time = 1.8 min.

Takt time = number of minutes available / no of units to be produced

= 5x5x60 /3000 = 0.5 min.

No. of workstations needed = 1.8 /0.5 = 3.6 =4 workstations

2 st tiud Spen 1.8 erriveny

Add a comment
Know the answer?
Add Answer to:
The Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT