Solution:
Budgeted fixed overhead cost = $9,200
Fixed overhead applied = Standard machine hours * Predetermined fixed overhead rate
= 1040 * $8 = $8,320
Fixed overhead production volume variance = Fixed overhead applied - Budgeted fixed overhead cost
= $8,320 - $9,200 = $880 Unfavorable
Hence last option is correct.
tual mochine hours Standard mochine hours allowed Denominator activity (machine hours) Actual fixed overhead costs Budgeted...
Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual foxed overhead costs Budgeted foed overhead costs Predetermined overhead rate ($i variable - $5 fixed 1075 4.800 What is the fixed overhead spending (budget, variance? $575 $575 $420 O $350
Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual foxed overhead costs Budgeted foed overhead costs Predetermined overhead rate ($i variable - $5 fixed 1075 4.800 What is the fixed overhead spending (budget, variance? $575 $575 $420 O $350
Actual machine hours 1,160 Standard machine hours allowed 1,310 Denominator activity (machine hours) 1,450 Actual fixed overhead costs $ 16,560 Budgeted fixed overhead costs $ 17,400 Predetermined overhead rate ($2 variable + $12 fixed) $ 14 What is the fixed overhead spending (price) variance? A. $840 favorable. B. $580 favorable. C. $280 favorable. D. $300 favorable.
1,020 Actual machine hours Standard machine hours allowed Denominator activity machine hours) Actual fixed overhead costs Budgeted faxed overhead costs Predetermined overhead rate ($2 variable 3.000 4080 $4 foed What is the production volume variance? $180 $440 $390 5260
The following information is available for Baxter Manufacturing for April: Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual fixed overhead costs 1,030 1,090 1,850 $7,600 $7, 400 %24 Budgeted fixed overhead costs Predetermined overhead rate ($1 variable + $4 fixed) Is the fixed overhead price (spending) variance for April favorable or unfavorable? Multiple Choice Unfavorable Favorable < Prev 23 of 34 Next >
Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 7,700 machine-hours. The budgeted fixed manufacturing overhead costs are $274,890. In April, the actual fixed manufacturing overhead costs were $280,280 and the standard machine-hours allowed for the actual output were 8,000 machine-hours. Required: a. Compute the budget variance for April. b. Compute the volume variance for April. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...
Behring Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual fixed manufacturing overhead costs for the most recent month appear below: Original Budget Actual Costs Fixed overhead cost: Supervision $4,680 $4,800 Utilities 6,120 5,820 Factory depreciation 21,240 20,720 Total fixed manufacturing overhead cost $32,040 $31,340 The company based its original budget on 3,600 machine-hours. The company actually worked 3,570 machine-hours during the month. The standard hours...
Asper Corporation has provided the following data for February. Denominator level of activity 9,300 machine-hours Budgeted fixed manufacturing overhead costs $ 284,020 Fixed component of the predetermined overhead rate $ 36.20 per machine-hour Actual level of activity 9,500 machine-hours Standard machine-hours allowed for the actual output 9,800 machine-hours Actual fixed manufacturing overhead costs $ 275,960 The budget variance for February is:
Asper Corporation has provided the following data for February. Denominator level of activity 9,700 machine-hours Budgeted fixed manufacturing overhead costs $ 288,420 Fixed component of the predetermined overhead rate $ 36.60 per machine-hour Actual level of activity 9,900 machine-hours Standard machine-hours allowed for the actual output 10,200 machine-hours Actual fixed manufacturing overhead costs $ 279,960 The budget variance for February is:
Norwall Company’s budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing overhead is $30,624 per month. The following information is available for a recent month: The denominator activity of 9,570 machine-hours is used to compute the predetermined overhead rate. At a denominator activity of 9,570 machine-hours, the company should produce 3,300 units of product. The company’s actual operating results were: Number of units produced 4,570 Actual machine-hours 10,090 Actual variable manufacturing overhead cost $ 14,630...