For quality test samples are taken at some time interval like every hour at following steps as follows:
1. Raw material quality test (Placed after quarrying limestone step)
2. After crushing limestones(Placed before storage and prehomozination of raw material)
3. After raw mill(Placed before filter)
4.Before preheating
5.While preheating(Before kiln)
6.Before clinker storage(After cooling )
7.After cement mill (Before packaging)
8.After storage (Before cement bag dispatch)
There are two method dry and wet testing method.This procedure uses X-ray in combination with QCX and QCS blending expert software and this method is short and precise. In addition, the plant has different types of XRF machines which are able to give accurate measurement, detect and control any instrument deviation.Wet method / Chemical method testing this procedure is used in the chemical analysis of cement,freelime, clinker and the remaining raw materials using chemicals and it is also categorized as volumetric and gravimetric.This is process is used for raw material, finished and semifinished products.
Below are available equipment and devices to test & control chemical and physical properties of cement, clinker, raw mix, Coal ,and raw materials.
Below is the manufacturing line for cement industry. Determine at which steps, sample quality tests should...
Question
Below is the manufacturing line for cement industry. Determine
at which steps, sample quality tests should be placed. State your
reason.
quarrying limestone crushing limestone raw mill mining iron ore sand storage and prehomogenization of raw material cement process-technology filter preheating pulverized coal clinker storage pulverized coal raw meal homogenization kiln secondary additives W calcination-burning raw meal to clinker cooling cement storage cement mills cement dispatch bags bulk bulk bulk/bags