Question

The scope statement is typically.... A. completed before the charter, but only in a rough manner, suitable for inclusion in t

0 0
Add a comment Improve this question Transcribed image text
Answer #1

B option

The scope statement is typically never completed before the charter. Scope statements are made in planning where as charters are made in initiating.

EXPLANATION

A scope statement gives a detailed explanation and description of the work that has to be carried out to deliver output. A project charter will be created in the initiating process group at the starting of a project.

  

Add a comment
Know the answer?
Add Answer to:
The scope statement is typically.... A. completed before the charter, but only in a rough manner,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT