13.Direct Labor Variances Bellingham Company produces a product that requires 3 standard direct labor hours per unit at a standa

14.Net Present Value A project has estimated annual net cash flows of $5,000 for two years and is estimated to cost $30,000. Ass

15.Internal Rate of Return A project is estimated to cost $159,648 and provide annual net cash flows of $48,000 for six years. P

16.Zoe Corporation has the following information for the month of March: Cost of direct materials used in production $15,139 Dir

17.A quality control activity analysis indicated the following four activity costs of a hotel: Inspecting cleanliness of rooms $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Direct labor rate variance = (SR-AR)AH = (10-10.40)*11500 = 4600 U

Direct labor time variance = (SH-AH)SR = (3900*3-11500)*10 = -2000 F

Direct labor time variance = 2600 U

Note : Pls post each que individually as HOMEWORKLIB guidelines

Add a comment
Know the answer?
Add Answer to:
PLEASE HELP AND SHOW WORK, please highlight answers, THANK YOU!! 13. 14. 15. 16. 17. Direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 15 PLEASE HELP AND SHOW WORK, please highlight answers, THANK YOU!! Calculator Internal Rate of Retum...

    15 PLEASE HELP AND SHOW WORK, please highlight answers, THANK YOU!! Calculator Internal Rate of Retum A project is estimated to cost $159,648 and provide annual net cash flows of $48,000 for six years. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 4 3.465 3.170 3.037 2.855 2.589 5 4.212 3.791 3.605 3.353 2.991...

  • PLEASE HELP AND SHOW WORK, please highlight answers, THANK YOU!! 14 Net Present Value A project...

    PLEASE HELP AND SHOW WORK, please highlight answers, THANK YOU!! 14 Net Present Value A project has estimated annual net cash flows of $5,000 for two years and is estimated to cost $30,000. Assume a minimum acceptable rate of return of 6%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Present Value of an Annuity of $1 at Compound Interest Year 6% 12% 15% 20% 10% 2.106 4.212 1 0.943 0.909 0.893 0.870 0.833...

  • Part A - Net Present Value A project has estimated annual net cash flows of $10,000 for one years and is estimated to co...

    Part A - Net Present Value A project has estimated annual net cash flows of $10,000 for one years and is estimated to cost $50,000. Assume a minimum acceptable rate of return of 10%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402...

  • Net Present Value—Unequal Lives Project 1 requires an original investment of $79,500. The project will yield...

    Net Present Value—Unequal Lives Project 1 requires an original investment of $79,500. The project will yield cash flows of $11,000 per year for 9 years. Project 2 has a computed net present value of $21,200 over a seven-year life. Project 1 could be sold at the end of seven years for a price of $57,000. Use the Present Value of $1 at Compound Interest and the Present Value of an Annuity of $1 at Compound Interest tables shown below. Year...

  • A project is estimated to cost $413,780 and provide annual net cash flows of $85,000 for...

    A project is estimated to cost $413,780 and provide annual net cash flows of $85,000 for seven years. Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 4 3.465 3.170 3.037 2.855 2.589 5 4.212 3.791 3.605 3.353 2.991 6 4.917 4.355 4.111 3.785 3.326 7 5.582 4.868 4.564 4.160 3.605 8 6.210 5.335 4.968 4.487 3.837 9 6.802 5.759 5.328 4.772 4.031 10 7.360...

  • A project is estimated to cost $379,704 and provide annual net cash flows of $78,000 for...

    A project is estimated to cost $379,704 and provide annual net cash flows of $78,000 for seven years. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 3.465 3.170 3.037 2.855 2.589 5 4.212 3.791 3.605 3.353 2.991 6 4.917 4.355 4.111 3.785 3.326 7 5.582 4.868 4.564 4.160 3.605 8 6.210 5.335 4.968 4.487...

  • Net Present Value A project has estimated annual net cash flows of $13,750 for two years...

    Net Present Value A project has estimated annual net cash flows of $13,750 for two years and is estimated to cost $32,500. Assume a minimum acceptable rate of return of 20%. Use the Present Value of an Annuity of $1 at Compound Interest table below Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 0.870 0.833 0.943 1.833 2.673 1.528 1.626 2.283 2.106 0.909 1.736 2.487 3.170 3.791 4.355 3.465 0.893 1.690 2.402...

  • A project has estimated annual net cash flows of $6,250 for five years and is estimated...

    A project has estimated annual net cash flows of $6,250 for five years and is estimated to cost $32,500. Assume a minimum acceptable rate of return of 15%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 4 3.465 3.170 3.037 2.855 2.589 5 4.212 3.791 3.605 3.353 2.991 6 4.917...

  • Net Present Value A project has estimated annual net cash flows of $5,000 for nine years...

    Net Present Value A project has estimated annual net cash flows of $5,000 for nine years and is estimated to cost $30,000. Assume a minimum acceptable rate of return of 12%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 4...

  • Net Present Value A project has estimated annual net cash flows of $6,250 for one years...

    Net Present Value A project has estimated annual net cash flows of $6,250 for one years and is estimated to cost $50,000. Assume a minimum acceptable rate of return of 10%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 3.465 3.170...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT