Question

Three teams in the Agile Release Train are working on the same Feature. Team A is...

  1. Three teams in the Agile Release Train are working on the same Feature. Team A is a component team, and Team B and Team C are feature teams. During PI planning, Team B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A’s piece in the first week of the IP Iteration. Why is this an anti-pattern.
  1. Because the teams managed their dependencies and planned their integration timing during PI planning
  2. Because work should not be planned for the IP iteration
  3. Because Product Manager accepted each team’s final plan at the end of PI Planning Day 2.
  4. Because each feature team needs to integrate with the component team
  5. Because each feature team need to integrate with the component team
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Anti pattern in agile is something which goes beyond the plan and makes things worsen.

In this scenario, all the teams need to integrate with each other. For which there should be proper planning.

It is not like we plan something and look at it at the end of interation 5. This worsens the situation.

One has to conduct daily standups and at the end of every iteration, one has to give something deliverable.

Thus, if I talk about this situation, definitely planning is also wrong. Things can't be delayed till IP toleration. Proper testing has to be done before that only.

But main reason is because features need to be integrated with each other. Otherwise it can go live anytime.

Hope it helps!

Please upvote if you like it.

You can comment in case of any issue

Thanks!

Add a comment
Know the answer?
Add Answer to:
Three teams in the Agile Release Train are working on the same Feature. Team A is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • Who do you think are top 3 stakeholder groups Now that you are familiar with the...

    Who do you think are top 3 stakeholder groups Now that you are familiar with the project, what are some areas that are more likely to change? What are ways to monitor the effectiveness of stakeholder engagement? CASE STUDY VIII. Integration Management About Global Information Store Introduction In the relaunch of the ERP system, now with Ms. Adriana Holmes as the new CPO, the project team reexamined and refreshed the business case. After a detailed analysis, the team agreed to...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

  • The activity An EHR was implemented at the General Hospital one year ago, before you were...

    The activity An EHR was implemented at the General Hospital one year ago, before you were hired. The implementation process did not go smoothly and now there are strong EHR advocates and strong EHR-dissenters on the team. The CEO wants to move forward with an implementation of the bar-coded medication administration feature of the EHR, but the director of nursing does not. You have been asked to manage the implementation and see that it is successful. You will first need...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • LO 2 8-47 Target costing Mercedes-Benz All Activity Vehicle (AAV)'3 Introduction During the recession beginning in...

    LO 2 8-47 Target costing Mercedes-Benz All Activity Vehicle (AAV)'3 Introduction During the recession beginning in the early 1990s, Mercedes-Benz (MB) struggled with product development, cost efficiency, material purchasing, and problems in adapting to changing mar- kets. In 1993, these problems caused the worst sales slump in decades, and the luxury car maker lost money for the first time in its history. Since then, MB has streamlined the core business, re- duced parts and system complexity, and established simultaneous engineering...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • Case 34 Emirates Airline Emirates Airline was one of the three Middle East carriers that were sin...

    Case 34 Emirates Airline Emirates Airline was one of the three Middle East carriers that were singled out by the largest US airlines in the report that was released on March 5, 2015. The report charged that that the flagship airline of Dubai, along with Etihad Airways and Qatar Airways, had received over $42 billion in government subsidies and tax breaks since 2004. Claiming that this gave an unfair advantage to these state-owned airlines, the US airlines demanded that the...

  • Discussion questions 1. What is the link between internal marketing and service quality in the ai...

    Discussion questions 1. What is the link between internal marketing and service quality in the airline industry? 2. What internal marketing programmes could British Airways put into place to avoid further internal unrest? What potential is there to extend auch programmes to external partners? 3. What challenges may BA face in implementing an internal marketing programme to deliver value to its customers? (1981)ǐn the context ofbank marketing ths theme has bon pururd by other, nashri oriented towards the identification of...

  • Read the Article posted below, then answer the following questions: Mergers & acquisitions are a major...

    Read the Article posted below, then answer the following questions: Mergers & acquisitions are a major form of corporate diversification strategy, identify and discuss the top three reasons why most (50-60%) of acquisitions fail to create shareholder value. What are the five major components of “CEMEX Way” and why has this approach been so successful in post-acquisition integration? In your opinion, what can other companies learn from the “CEMEX Way” as a benchmark for acquisition management? Article: CEMEX: Globalization "The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT