Question

When applying NPV and IRR methods to evaluate potential projects, both require use of a discount...

When applying NPV and IRR methods to evaluate potential projects, both require use of a discount rate. What is the discount rate used for NPV and IRR, respectively?

Group of answer choices

IRR; cost of capital

Cost of capital; IRR

Cost of capital; cost of capital

Cost of equity; cost of capital

0 0
Add a comment Improve this question Transcribed image text
Answer #1

While Calculating NPV, Cash flows are discounted using Cost of Capital.

IRR is compared to Cost of Capital to determine whether the Project should be accepted or not.

Therefore, Discount rate used for NPV and IRR are Cost of Capital.

Answer : Cost of Capital, Cost of Capital

Add a comment
Know the answer?
Add Answer to:
When applying NPV and IRR methods to evaluate potential projects, both require use of a discount...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • When applying NPV and IRR methods to evaluate potential projects, both require use of a discount...

    When applying NPV and IRR methods to evaluate potential projects, both require use of a discount rate. What is the discount rate used for NPV and IRR, respectively? A) Cost of equity; cost of capital B) IRR; cost of capital C) Cost of capital; cost of capital D) Cost of capital; IRR

  • Imagine that two mutually exclusive projects have yielded NPV, PI, and IRR estimations as shown in...

    Imagine that two mutually exclusive projects have yielded NPV, PI, and IRR estimations as shown in the table below: Decision Method Project SDX Project TGL NPV $2,100.87 $2,099.13 PI 1.68 1.44 IRR 14.56% 19.76% Suppose that the minimum required rate of return is 10.00% for both projects. Based on the capital budgeting decision methods presented in the data table above, determine the better alternative project to invest in. Group of answer choices 1) Project TGL 2)Project SDX 3)Neither one of...

  • When do ranking conflicts arise in IRR versus NPV? Group of answer choices When the first...

    When do ranking conflicts arise in IRR versus NPV? Group of answer choices When the first cash flow is negative and the remaining cash flows are positive. When projects are independent of one another. When projects are mutually exclusive and the cost of capital is to the left of the crossover point. All of the above can result in conflicts.

  • 6. If IRR and NPV give different answers, you should to discount future cash a. use...

    6. If IRR and NPV give different answers, you should to discount future cash a. use IRR always b. use NPV always c. Use IRR if mutually exclusive projects d. use IRR if independent projects 7. If you are expressing all cash flows in future dollars, you use the The Innominal restro a. The IRR interest rate b. The nominal interest rate c. The real interest rate d. The corrected interest rate multiple assumptions to see how it affects NPV...

  • Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...

    Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is: CFt is the expected cash flow in Period t and cash outflows are treated...

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • Please use Excel to solve. NPV and IRR for Mutually Exclusive Projects 10. A company is...

    Please use Excel to solve. NPV and IRR for Mutually Exclusive Projects 10. A company is considering two mutually exclusive projects, A and B. Project A requires an initial investment of $200, followed by cash flows of $185, $40, and $15. Project B requires an initial investment of $200, followed by cash flows of S0, $50, and $230. What is the NPV and IRR for each of the projects? Which project should the company choose? The firm's cost of capital...

  • 8.11 NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the...

    8.11 NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation (BRC). Both projects require an annual return of 14 percent. Main Page Year Deepwater Fishing New Submarine Ride Incremental (Ride-Fishing) 0 $(850,000.00) $(1,650,000.00) $(800,000.00) 1 $320,000.00 $810,000.00 $490,000.00 2 $470,000.00 $750,000.00 $280,000.00 3 $410,000.00 $690,000.00 $280,000.00 Discount Rate IRR NPV As a financial analyst for BRC, you are asked the following questions: a. If your decision rule is to accept the...

  • 1. Calculate the net present value (NPV) for both projects, and determine which project should be...

    1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. 2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR. 3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar. Please show all work. Thank you. Use...

  • IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate...

    IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-on a bond. The equation for calculating the IRR is: ;that forces the PV of its inflows to equal its cost. CF2 CFN 1 IRF 1 IRF 1IR CFt t-1 (1 +IRR) CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT