Question

Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs...

Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday​ morning, and she must decide in what order to write the code. Assume that all jobs arrived today​ (day 1 and hour​ 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an​ 8-hour day and today is a work day.

JOB DUE DATE (HOURS HENCE) DURATION (HOURS REQUIRED)
A 34 20
B 24 10
C 8 4
D 20 1
E 14 5

a. Sequence the jobs according to EDD?

b. What is the average competition (flow) time?

c. What is the average job lateness?

d. What is the average number of jobs in the system?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a= Sequence as per EDD will be the ascending order of due date. So the sequence will be=C-E-D-B-A

Activity In Out Due date Lateness
C 0 4 8 0
E 4 4+5=9 14 0
D 9 9+1=10 20 0
B 10 10+10=20 24 0
A 20 20+20=40 34 6

Answer b- Averahe completion time = (4+9+10+20+40)/5=16.6

Answer c= Average job lateness = 6/5=1.2

Answer d= average number of jobs= (4+9+10+20+40)/(20+10+4+1+5)=2.08

Add a comment
Know the answer?
Add Answer to:
Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro-...

    Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro- cessed as of 8 A.M. today (day 23) at its bottleneck opera- tion. The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Job А 11 10 22 10 8 В 13 8...

  • Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...

    Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...

  • Data Analysis Project Part 1 Custom Fabric Ventures is a small company that produces fabric-based wardrobe...

    Data Analysis Project Part 1Custom Fabric Ventures is a small company that produces fabric-based wardrobe accessories (such as, handbags, scarves, and headbands) and home accessories (such as placemats, pillows, and window treatments).   The company keeps a limited number of popular items in stock, but primarily produces custom orders. Customers are able to choose from a wide selection of styles, sizes, and fabrics for each type of product. Most of the company’s customers are small boutiques, home décor shops, and home-decorators...

  • 2) compute contribution margin for each channel 3) compute break even point (in terms of number...

    2) compute contribution margin for each channel 3) compute break even point (in terms of number of orders and dollars) for each distribution channel (HINT  - Fixed costs are all trade show expenses.  Use depreciation for the booth as a fixed cost.  The booth cost should be considered an investment not a fixed cost) 4) Calculate the number of orders at a target profit of $100,000 5) Calculate the profitability for both the low and high order estimates We were...

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

  • A. Issues [1] In addition to damages for one year's notice period, can a trial judge...

    A. Issues [1] In addition to damages for one year's notice period, can a trial judge award significant damages for the mere fact of an employee's dismissal, or for the stigma that that dismissal brings? Or for the employer thereafter competing with the ex-employee for the clients, before the ex-employee has got a new job? B. Basic Facts [2] This is an appeal from 2009 ABQB 591 (CanLII), 473 A.R. 254. [3] Usually a judgment recites facts before law. But...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT