Question

Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solanos machine center. Solanos machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241 Sequence Job Date Job Received 225 230 235 231 228 Job Due Date Duration (days) BR- 02 CX-01 DE-06 RG-05 SY -11 270 320 360 310 300 25 35 40 The total flow time for the sequence developed using the FCFS rule-days (round your response to two decimal places) The percentage utilization for the sequence developed using the FCFS rule-| response as a percentage rounded to two decimal places) % (enter your The average number of jobs in the system for the sequence developed using the FCFS rule- jobs (round your response to two decimal places) The average tardiness (job lateness) for the sequence developed using the FCFS ruledays (round your response to two decimal places). Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • a) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the...

    a) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the order is​ (assume that jobs came in the order in which they are listed in the​ table): Sequence Job 1 A 2 B 3 C 4 D 5 E The average tardiness​ (job lateness) for the sequence developed using the FCFS rule​ = ___ days ​(round your response to two decimal​ places). The following jobs are waiting to be processed at the same machine...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing...

    Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be prooessed at Rick Sclano's machine center. Solanos machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

  • The following jobs are waiting to be processed at Rick Carlson’s machine center.

    15.13 The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and sets fresh schedulesevery 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers.Job Date Job Received Production Days Needed Date Job DueBR-02 228...

  • Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago)...

    Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago) (hours from now) Order 1 0 2* 10 12 3 5 8 3 18 20 The due dates reflect the need for the order to be hours t its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due Using the FCFS (first come, first served) decision rule...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT