Question

The following jobs are waiting to be processed at Rick Carlson’s machine center.

15.13 The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and sets fresh schedulesevery 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers.
Job Date Job Received Production Days Needed Date Job Due
BR-02 228 15 300
CX-01 225 25 270
DE-06 230 35 320
RG-05 235 40 360
SY-11 231 30 310

a) Complete the table below. (Show your supporting calculations)
b) Which dispatching rule has the best score for flow time?
c) Which dispatching rule has the best score for utilization metric?
d) Which dispatching rule has the best score for lateness?
e) Which dispatching rule would you select? Support your decision
1 2
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

a.

To complete: The table given below.

Given information:

It is given that C machine center schedules for every 2 weeks. Today is 241st working day, and they are all set to schedule the jobs for next 2 weeks.

Job

Date job received

Production days needed

Date job due

B

228

15

300

C

225

25

270

D

230

35

320

R

235

40

360

S

231

30

310

Explanation:

Early due date:

The job with the earliest due date is selected first and the rest of the jobs are taken in an ascending order.

The order of selection of jobs using early due date method is:

Job sequence

Date job due

C

270

B

300

S

310

D

320

R

360

Table no: 1

Picture 22

Note: Flow time is the cumulative addition of production days needed / processing time (column 3).

Note: In column 6, the date job due (from column 5) is reduced by 240 since the job is started from day 241.

Note: In column 7, when subtracting flow time (column 4) and job starting date (column 6), assign 0 instead of negative numbers.

It is calculated that the total late days are 50. Refer to Table no: 1.

It is given that the total number of jobs is 5.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 1.

It is calculated that the sum of total flow time is 385 days. Refer to Table no: 1.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 1.

It is calculated that the sum of total flow time is385 days. Refer to Table no: 1.

Shortest processing time:

The job with shortest processing time is taken first and the rest of the jobs are taken in an ascending order.

The order of selection of jobs using shortest processing time method is:

Job sequence

Production days needed

B

15

C

25

S

30

D

35

R

40

Table no: 2

Picture 25

Note: Flow time is the cumulative addition of production days needed / processing time (column 3).

Note: In column 6, the date job due (from column 5) is reduced by 240 since the job is started from day 241.

Note: In column 7, when subtracting flow time (column 4) and job starting date (column 6), assign 0 instead of negative numbers.

It is calculated that the total late days are 60. Refer to Table no: 2.

It is given that the total number of jobs is 5.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 2.

It is calculated that the sum of total flow time is 375 days. Refer to Table no: 2.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 2.

It is calculated that the sum of total flow time is 375 days. Refer to Table no: 2.

Longest processing time:

The job with the longest processing time is taken first and the rest of the jobs are taken in a descending order.

The order of selection of jobs using longest processing time method is:

Job sequence

Production days needed

R

40

D

35

S

30

C

25

B

15

Table no: 3

Picture 28

Note: Flow time is the cumulative addition of production days needed / processing time (column 3).

Note: In column 6, the date job due (from column 5) is reduced by 240 since the job is started from day 241.

Note: In column 7, when subtracting flow time (column 4) and job starting date (column 6), assign 0 instead of negative numbers.

It is calculated that the total late days are 220. Refer to Table no: 3.

It is given that the total number of jobs is 5.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 3.

It is calculated that the sum of total flow time is 495 days. Refer to Table no: 3.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 3.

It is calculated that the sum of total flow time is 495 days. Refer to Table no: 3.

First come first serve method:

The processes for the job are done according to the order they arrive.

The order of selection of jobs using first come first serve method is:

Job sequence

Date job received

B

228

C

225

D

230

R

235

S

231

Table no: 4

Picture 31

Note: Flow time is the cumulative addition of production days needed / processing time (column 3).

Note: In column 6, the date job due (from column 5) is reduced by 240 since the job is started from day 241.

Note: In column 7, when subtracting flow time (column 4) and job starting date (column 6), assign 0 instead of negative numbers.

It is calculated that the total late days are 85. Refer to Table no: 3.

It is given that the total number of jobs is 5.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 4.

It is calculated that the sum of total flow time is 390 days. Refer to Table no: 4.

It is calculated that the total production days needed (processing time) is 145 days. Refer to Table no: 4.

It is calculated that the sum of total flow time is 390 days. Refer to Table no: 4.

Therefore, the completed table is:

Picture 13

b.

To determine: The dispatching rule that has the best score for flow time.

Given information:

It is given that C machine center schedules for every 2 weeks. Today is 241st working day, and they are all set to schedule the jobs for next 2 weeks.

Job

Date job received

Production days needed

Date job due

B

228

15

300

C

225

25

270

D

230

35

320

R

235

40

360

S

231

30

310

Explanation:

Now, find the dispatching rule that has best score for flow time.

Flow time shows the time taken for all the processes in the job. Least value denotes quick processing and completion of jobs, which is the best option. SPT has the least score for flow time compared to all other methods.

c.

To determine: The dispatching rule that has the best score for utilization metric.

Given information:

It is given that C machine center schedules for every 2 weeks. Today is 241st working day, and they are all set to schedule the jobs for next 2 weeks.

Job

Date job received

Production days needed

Date job due

B

228

15

300

C

225

25

270

D

230

35

320

R

235

40

360

S

231

30

310

Explanation:

Now, find the dispatching rule that has best score for utilization metric.

Utilization metric shows how effectively the jobs are done. Higher the score higher is the effectiveness. SPT has the highest score; therefore, it must be chosen.

d.

To determine: The dispatching rule that has the best score for lateness.

Given information:

It is given that C machine center schedules for every 2 weeks. Today is 241st working day, and they are all set to schedule the jobs for next 2 weeks.

Job

Date job received

Production days needed

Date job due

B

228

15

300

C

225

25

270

D

230

35

320

R

235

40

360

S

231

30

310

Explanation:

Now, find the dispatching rule that has best score for lateness.

Average job lateness shows the delay in the processing of the job. Lower the score quicker the jobs are done. EDD has the least score for average job lateness.

e.

To determine: The best dispatching rule.

Given information:

It is given that C machine center schedules for every 2 weeks. Today is 241st working day, and they are all set to schedule the jobs for next 2 weeks.

Job

Date job received

Production days needed

Date job due

B

228

15

300

C

225

25

270

D

230

35

320

R

235

40

360

S

231

30

310

Explanation:

Now, find the best dispatching rule.

Either SPT or EDD can be chosen, since SPT has the best score for flow time and utilization rate and EDD has the best score for job lateness.

Add a comment
Know the answer?
Add Answer to:
The following jobs are waiting to be processed at Rick Carlson’s machine center.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...

    Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...

  • Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing...

    Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be prooessed at Rick Sclano's machine center. Solanos machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • SIDDHERTHA CAN YOU SOLVE THIS BY EXPLAINING ALL FORMULAS AND ANSWERS obs are waiting to be processed at your work center, which cleans valve body castings Job numbers are All assigned sequentially up...

    SIDDHERTHA CAN YOU SOLVE THIS BY EXPLAINING ALL FORMULAS AND ANSWERS obs are waiting to be processed at your work center, which cleans valve body castings Job numbers are All assigned sequentially upon arrival in the facility (a missing number means that job does not require your work center) dates are specified as days from today Due Date Duration 43 10 101 34 37 32 7 12 104 7 107 108 oeos bcesed soseudra to tedhduing rule? a. In what...

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • Given the following set of jobs waiting to run on a machine, use the Slack (least...

    Given the following set of jobs waiting to run on a machine, use the Slack (least slack time remaining) dispatching rule to sequence the jobs. Job Days Until Due Date Processing Time A 35 30 B 27 17 C 33 30 D 41 25 A. A,B,C,D B. B,C,D,A C. C,A,B,D D. B,C,A,D E. none of the above

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT