Question

Given the following set of jobs waiting to run on a machine, use the Slack (least...

Given the following set of jobs waiting to run on a machine, use the Slack (least slack time remaining) dispatching rule to sequence the jobs.

Job Days Until Due Date Processing Time
A 35 30
B 27 17
C 33 30
D 41 25
A.

A,B,C,D

B.

B,C,D,A

C.

C,A,B,D

D.

B,C,A,D

E.

none of the above

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Under the Slack (least slack time remaining) dispatching rule to sequence the jobs, we need to calculate the Slack time for each of the jobs.

Slack time remaining = Time remaining(Days) before the due date - Processing time

Job Days until the due date Processing time Slack time remaining
A 35 30 = 35 - 30 = 5
B 27 17 = 27 - 17 = 10
C 33 30 = 33 - 30 = 3
D 41 25 = 41 - 25 = 16

Hence under the Slack dispatching rule to sequence the jobs, the sequence is C, A, B, D

Hence the correct answer is option C.

Add a comment
Know the answer?
Add Answer to:
Given the following set of jobs waiting to run on a machine, use the Slack (least...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following jobs are waiting to be processed at Rick Carlson’s machine center.

    15.13 The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and sets fresh schedulesevery 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers.Job Date Job Received Production Days Needed Date Job DueBR-02 228...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • 1. Five jobs are waiting to be processed. Their processing times and due dates are given...

    1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • please answer this ABC's machine shop is considering the use of priority scheduling rule in the...

    please answer this ABC's machine shop is considering the use of priority scheduling rule in the fabrication shop and must decide whether to use: a. Critical ratio (CR) Earliest due date (EDD) C. Shortest operation next (SON)/Shortest processing time 9SPT) d. Order Slack Order No. Total Remaining Time Remaining Current operation Manufacturing until Due Date Processing time Time (days) (days) (days) А 12 15 10 14 D 18 15 19 Using the four sequencing rules, compute the scheduling priority for...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness...

    If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness (in days) is (assume zero for today's date) Job Processing Time (days) Due Date A 8 12 B 6 15 C 11 17 D 7 10 E 3 8

  • Determine the processing sequence that would result using the Slack per operation rule. Given the information...

    Determine the processing sequence that would result using the Slack per operation rule. Given the information in the following table Remaining Number of Job Time (Days) Due Date Operations Remaining Processing 8 6 10 12 10 8 Determine the processing sequence that would result using the Slack per operation rule. The sequence is (Click to select) v

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at...

    Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival): Job Processing Time (Days) Due Date (days from Now) A 2 2 B 5 6 C 6 10 D 9 6 E 4 8 What is the average flow time for the shortest processing time (SPT) rule schedule?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT