Question

Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing ti

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answes ophon c shorlest procesing time dispatching nule tendy to minimize job flow time. The order is C, A, E B, D. re, Job

Add a comment
Know the answer?
Add Answer to:
Five jobs are waiting to be processed. Their processing times and due dates are given below....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Five jobs are waiting to be processed. Their processing times and due dates are given...

    1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...

  • Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at...

    Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival): Job Processing Time (Days) Due Date (days from Now) A 2 2 B 5 6 C 6 10 D 9 6 E 4 8 What is the average flow time for the shortest processing time (SPT) rule schedule?

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • Suppose we have five jobs to be processed on a single machine. The processing times and...

    Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown below Job 2 3 4 Processing Time 2 6 5 4 Due Date 10 11 15 4 13 Find a schedule that minimizes the number of tardy jobs

  • The following jobs are waiting to be processed at Rick Carlson’s machine center.

    15.13 The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and sets fresh schedulesevery 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers.Job Date Job Received Production Days Needed Date Job DueBR-02 228...

  • Given the following set of jobs waiting to run on a machine, use the Slack (least...

    Given the following set of jobs waiting to run on a machine, use the Slack (least slack time remaining) dispatching rule to sequence the jobs. Job Days Until Due Date Processing Time A 35 30 B 27 17 C 33 30 D 41 25 A. A,B,C,D B. B,C,D,A C. C,A,B,D D. B,C,A,D E. none of the above

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and...

    Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and times are expressed in terms of hours. All pertinent data are given in the following table. Job Time Since Job Arrived Processing Time Due Date A 8 3 10 B 7 6 14 C 6 3 2 D 4 2 6 E 1 5 16 Using the information in the Table and the SPT rule, what is the average flow time? Fewer than or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT