Problem #1
Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero.
Job |
1 |
2 |
3 |
4 |
5 |
Processing time |
3 |
6 |
5 |
4 |
2 |
Due date |
4 |
8 |
12 |
21 |
15 |
In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs.
A) Shortest Processing Time
B) Early Due Date
A)
SPT
Job | Processing time | Due date | Start | Finish | Flow time | Tardiness |
5 | 2 | 15 | 0 | 2 | 2 | 0 |
1 | 3 | 4 | 2 | 5 | 5 | 1 |
4 | 4 | 21 | 5 | 9 | 9 | 0 |
3 | 5 | 12 | 9 | 14 | 14 | 2 |
2 | 6 | 8 | 14 | 20 | 20 | 12 |
Avg. | 10 | 3 |
Average flow time = 10
Average tardiness = 3
Average number of tardy jobs = 3
B)
EDD
Job | Processing time | Due date | Start | Finish | Flow time | Tardiness |
1 | 3 | 4 | 0 | 3 | 3 | 0 |
2 | 6 | 8 | 3 | 9 | 9 | 1 |
3 | 5 | 12 | 9 | 14 | 14 | 2 |
5 | 2 | 15 | 14 | 16 | 16 | 1 |
4 | 4 | 21 | 16 | 20 | 20 | 0 |
Avg. | 12.4 | 0.8 |
Average flow time = 12.4
Average tardiness = 0.80
Average number of tardy jobs = 3
Calculations:
Problem #1 Five jobs are to be processed through a single machine. The processing times and...
Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown below Job 2 3 4 Processing Time 2 6 5 4 Due Date 10 11 15 4 13 Find a schedule that minimizes the number of tardy jobs
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...
1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...
Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...
make sure the answer is correct 100% Exercise 1: Suppose that 5 jobs will be processed on a single machine. The jobs are ready for processing at time. The other job characteristics are as shown in the table below. Find the: Mean flow time, Average tardiness and number of tardy jobs using: a. FCFS (30 Points) b. EDD (30 Points) Job Processing Time Due Date 10 20 B 20 30 С 4 10 D 16 24 E 6 8 F...
Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours) (Hours) Job 3.5 2.0 4.5 5.0 2.5 6.0 18 20 Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. a-1. Sequence for First come, first served (Click to select) Sequence for Shortest processing time Click to select) Sequence for Earliest due date (Click to select) Click to select) Sequence...
Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e., if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness of...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 8 12 B 4 9 C 3 6 D 7 7 E 5 20 Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____. a. more than 14 but less than...
The following table contains information concerning four jobs that are awaiting processing at a work center. Job Job Time (Days) Due Date (Days) A 14 20 B 10 16 C 7 15 D 6 17 a. Sequence the jobs using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. Assume the list is by order of arrival. Sequence for First come, first served (Click to select) A-B-C-D D-C-B-A C-B-D-A A-C-D-B Sequence for Shortest processing time (Click...
Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival): Job Processing Time (Days) Due Date (days from Now) A 2 2 B 5 6 C 6 10 D 9 6 E 4 8 What is the average flow time for the shortest processing time (SPT) rule schedule?