Question

Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours) (Hours) Job 3.5 2.0 4.5 5.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
a-1
1
The processing sequence is the sequence for which jobs should be processed first
If the sequence is first come, first served. In this case we would go as per the sequence given
Therefore, sequence for first come, first served would be a-b-c-d-e-f
2
If the processing sequence is job which takes shortest processing time. In this case the jobs which take lower time are processes first
Therefore, sequence would be b-e-a-c-d-f
3
If the processing sequence is job which has earliest due date, in this case the jobs which has lowest due date is processed first
Therefore, sequence would be e-b-a-c-f-d
4
Calculation of CR ratio so as to determine the processing sequence
Calculating iitial critical ratios at hour 0
Job Processing time (hours) Due date (hours) Critical ratio calculation CR
a 3.5 7 (7-0)/3.5 2.00
b 2 6 (6-0)/2 3.00
c 4.5 18 (18-0)/4.5 4.00
d 5 22 (22-0)/5 4.40
e 2.5 4 (4-0)/2.5 1.60 lowest
f 6 20 (20-0)/6 3.33
Job e is scheduled first
At hour 0 + 2.5 = 2.50 Job e completed, the critical ratio calculation is
Job Processing time (hours) Due date (hours) Critical ratio calculation CR
a 3.5 7 (7-2.5)/3.5 1.29 lowest
b 2 6 (6-2.5)/2 1.75
c 4.5 18 (18-2.5)/4.5 3.44
d 5 22 (22-2.5)/5 3.90
f 6 20 (20-2.5)/6 2.92
Job a is scheduled second
At hour 2.50 + 3.50 = 6 Job a completed, the critical ratio calculation is
Job Processing time (hours) Due date (hours) Critical ratio calculation CR
b 2 6 (6-6)/2 0.00 lowest
c 4.5 18 (18-6)/4.5 2.67
d 5 22 (22-6)/5 3.20
f 6 20 (20-6)/6 2.33
Job b is scheduled third
At hour 6+2 = 8 job b is completed, the critical ratio calculation is
Job Processing time (hours) Due date (hours) Critical ratio calculation CR
c 4.5 18 (18-8)/4.5 2.22
d 5 22 (22-8)/5 2.80
f 6 20 (20-8)/6 2.00 lowest
Job f is scheduled fourth
At hour 8+6 = 14, job f is completed, the critical ratio calculation is
Job Processing time (hours) Due date (hours) Critical ratio calculation CR
c 4.5 18 (18-14)/4.5 0.88888889 lowest
d 5 22 (22-14)/5 1.6
Job c is scheduled fifth
Therefore, job d is scheduled sixth
The processing sequence would be e-a-b-f-c-d
a-2
First come first served
We will have to calculate flow time and tardy hours
Job flow time is the cumulative job time of processing sequence
Tardy time = Flow time - due date
Job Job time (hours) Due date (hours) Flow time Tardy days
a 3.5 7.0 3.5 0.0
b 2.0 6.0 5.5 0.0
c 4.5 18.0 10.0 0.0
d 5.0 22.0 15.0 0.0
e 2.5 4.0 17.5 13.5
f 6.0 20.0 23.5 3.5
23.5 75.0 17
Average job flow time = Total job flow time/Number of jobs 23.50/6 12.50
Average job tardiness = Total job tardiness/Number of jobs 17/6 2.83
Shortest processing time
sequence is b-e-a-c-d-f
Job Job time (hours) Due date (hours) Flow time Tardy days
b 2 6 2 0
e 2.5 4 4.5 0.5
a 3.5 7 8 1
c 4.5 18 12.5 0
d 5 22 17.5 0
f 6 20 23.5 3.5
23.5 68 5
Average job flow time = 77/6 11.33
Average job tradiness = 5/6 0.83
Earliest due date
Therefore, sequence would be e-b-a-c-f-d
Job Job time (hours) Due date (hours) Flow time Tardy days
e 2.5 4 2.5 0
b 2 6 4.5 0
a 3.5 7 8 1
c 4.5 18 12.5 0
f 6 20 18.5 0
d 5 22 23.5 1.5
23.5 69.5 2.5
Average job flow time = 69.5/6 11.58
Average job tradiness = 5/6 0.42
Critical ratio
The processing sequence would be e-a-b-f-c-d
Job Job time (hours) Due date (hours) Flow time Tardy days
e 2.5 4 2.5 0
a 3.5 7 6 0
b 2 6 8 2
f 6 20 14 0
c 4.5 18 18.5 0.5
d 5 22 23.5 1.5
23.5 72.5 4
Average job flow time = 72.5/6 12.08
Average job tradiness = 3.5/6 0.67
First come first served Shortest processing time Earliest due date Critical ratio
Average flow time 12.50 11.33 11.58 12.08
Average job tradiness 2.83 0.83 0.42 0.67
Add a comment
Know the answer?
Add Answer to:
Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following table contains information concerning four jobs that are awaiting processing at a work center....

    The following table contains information concerning four jobs that are awaiting processing at a work center. Job Job Time (Days) Due Date (Days) A 14 20 B 10 16 C 7 15 D 6 17 a. Sequence the jobs using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. Assume the list is by order of arrival. Sequence for First come, first served   (Click to select)   A-B-C-D   D-C-B-A   C-B-D-A   A-C-D-B Sequence for Shortest processing time   (Click...

  • Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38...

    Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e., if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness of...

  • Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due...

    Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due Date 9 10 38 15 43 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e, if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness...

  • Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago)...

    Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago) (hours from now) Order 1 0 2* 10 12 3 5 8 3 18 20 The due dates reflect the need for the order to be hours t its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due Using the FCFS (first come, first served) decision rule...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • What would be the sequence of the following jobs if you did them in Earliest Due...

    What would be the sequence of the following jobs if you did them in Earliest Due Date sequence? Job A B Processing Time Days Due from Today 18 24 16 16 26 10 14 12 21 30 С D E OE,A,D,B,C E,D,A,C,B OC,D,B,A,E, C.B.D.A,E Question 6 (10 points) You have 5 jobs to do. What would be the sequence if you chose to do a Shortest Processing Time Approach? Job Processing Time Days Due from Today А 24 30 B...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT