Question

Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due Date 9 10 38 15 43 35 40 25 20 40 Assume tha
(3 points) Generate a schedule that minimizes the maximum tardiness. Break ties with the smallest job number first. c) d) (3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Minimum Flow Time is achieved with the SPT (shortest processing time) method. Mimimising maximum tardiness is with the EDD (earliest due date method). workings as follows :

a and b
Shortest Processing Time (SPT)
Job In Out Due Date Tardiness
2 0 3 40 -37
1 3 7 35 -28
7 7 13 40 -27
3 13 20 44 -24
8 20 27 22 5
5 27 35 20 15
4 35 44 25 19
9 44 54 38 16
6 54 69 43 26
Mean Flow Time 30.22222
Mean Tardiness -3.88889
Maximum Tardiness 26 days
c and d
Earliest Due Date Method
Job Start End Due Date Tardiness
5 0 8 20 -12
8 8 15 22 -7
4 15 24 25 -1
1 24 28 35 -7
9 28 38 38 0
2 38 41 40 1
7 41 47 40 7
6 47 62 43 19
3 62 69 44 25
Mean Flow Time 36.88889
Mean Tardiness 2.777778
Maximum Tardiness 25 days
Add a comment
Know the answer?
Add Answer to:
Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38...

    Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e., if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness of...

  • Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours...

    Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours) (Hours) Job 3.5 2.0 4.5 5.0 2.5 6.0 18 20 Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. a-1. Sequence for First come, first served (Click to select) Sequence for Shortest processing time Click to select) Sequence for Earliest due date (Click to select) Click to select) Sequence...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • Suppose we have five jobs to be processed on a single machine. The processing times and...

    Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown below Job 2 3 4 Processing Time 2 6 5 4 Due Date 10 11 15 4 13 Find a schedule that minimizes the number of tardy jobs

  • 1. Five jobs are waiting to be processed. Their processing times and due dates are given...

    1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • Given the following jobs to schedule (already ordered): job numberstart time finish timevalue 6 1...

    Given the following jobs to schedule (already ordered): job numberstart time finish timevalue 6 10 2 6 4 8 6 What will the Pü) values in the predecessor table be? Enter the first 3 values, for jobs 1 to 3 (in that order), here: Enter the next 3 values, for jobs 4 to 6 (in that order), here: Question 16 (6 points) from the previous question, what values will be in the optimal benefit table, B? Enter the first 3...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT