Question

Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown b

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Make span = 6+3+5+4+2 = 20

Maximum due date = 15

Maximum due date is less than the Makespan. Therefore, there will be atleast one job, whose flow time will exceed the due date. In other words, there is at least one tardy job, regardless of schedule.

In order to minimize the number of tardy jobs, jobs must be scheduled in such an order that flow time of as many jobs as possible remain less than their due date.

There are two possible schedules, which result in just one tardy job. These schedules are:

(1) 2-3-5-4-1 , and

(2) 2-5-3-4-1

The table showing the calculation of flow time and tardiness is following:

Job Processing Due Flow Time Tardiness time Pidate Di Fi = Di+F-1 Li = MAX(0,Fi-Di) 4 13 3 5 0 0

Flow time of each job is equal to the running sum of processing times of all the jobs from the first job scheduled upto that job. For example, flow time of job 3 in the above sequence = 3+2+5 = 10 . Flow time of Job 1 = 3+2+5+4+6 = 20

Tardiness is the difference between flow time and due date, if flow time is greater than due date, otherwise tardiness is 0

Mathematical formulas are shown in the header.

Using any of these schedules, there is only one tardy job.

Add a comment
Know the answer?
Add Answer to:
Suppose we have five jobs to be processed on a single machine. The processing times and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • 1. Five jobs are waiting to be processed. Their processing times and due dates are given...

    1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • make sure the answer is correct 100% Exercise 1: Suppose that 5 jobs will be processed...

    make sure the answer is correct 100% Exercise 1: Suppose that 5 jobs will be processed on a single machine. The jobs are ready for processing at time. The other job characteristics are as shown in the table below. Find the: Mean flow time, Average tardiness and number of tardy jobs using: a. FCFS (30 Points) b. EDD (30 Points) Job Processing Time Due Date 10 20 B 20 30 С 4 10 D 16 24 E 6 8 F...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38...

    Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e., if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness of...

  • 1. Suppose you have four jobs that must be processed, with the following table giving their...

    1. Suppose you have four jobs that must be processed, with the following table giving their charac- teristics(all times in hours): Each job can be processed on any of three identical machines; to be Job 1 23 4 Processing time 21.524 | 2 | 0 | 0.5 | 1 Release time Processing time 5346 finished, a job must be processed for its entire processing time, but this processing time can be interrupted and even moved to a different machine if...

  • Determine the processing sequence for the five jobs to be processed on the two work centers...

    Determine the processing sequence for the five jobs to be processed on the two work centers shown below using Johnson's Rule. What is the total throughput time. Show your work. Job Center1 Center2 A 6 7 B 10 9 C 12 8 D 5 11 E 13 4

  • Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due...

    Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due Date 9 10 38 15 43 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e, if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness...

  • Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at...

    Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival): Job Processing Time (Days) Due Date (days from Now) A 2 2 B 5 6 C 6 10 D 9 6 E 4 8 What is the average flow time for the shortest processing time (SPT) rule schedule?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT