Determine the processing sequence for the five jobs to be processed on the two work centers shown below using Johnson's Rule. What is the total throughput time. Show your work.
Job |
Center1 | Center2 |
A |
6 |
7 |
B |
10 |
9 |
C |
12 |
8 |
D |
5 |
11 |
E |
13 |
4 |
"As per Johnson’s Rule, Select the job with the shortest
operation time. If the shortest operation time is for center1, then
schedule that job first. If It is for the center2, then schedule
that job at the last. If there is a tie, prefer the job on center1.
Eliminate the assigned job from further consideration."
Here,
E at centre 2 has the shortest operation time of 4, so it will be
scheduled at last that is fifth.
D at centre 1 has the next shortest operation time of 5, so it will be scheduled at first.
A at centre 1 has the next shortest operation time of 6, so it will be scheduled at second.
C at centre 2 has the next shortest operation time of 8, so it will be scheduled at second last that is fourth.
Next shortest operation time is 9 of Job B at centre 2 , so it will be scheduled at third.
Processing sequence for the five jobs to be processed on the two
work centers using Johnson's Rule is :
D-A-B-C-E
Total throughput time calculation
Centre 1 - Cumulative operation time
D : 5
A : 11 (5+6)
B : 21 (11+10)
C : 33 (21+12)
E : 46 (33+13)
Centre 2 - Cumulative operation time
D : 16 (11+5) For centre 2's first job we will add operation time
of first centre as well. Then we will take Cumulative of centre 2
operation times.
A : 23 (16+7)
B : 32 (23+9)
C : 40 (32+8)
E : 44 (40+4)
So, total throughput time is 44 (maximum value)
Determine the processing sequence for the five jobs to be processed on the two work centers...
2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate total throughput (makespan) time. (12 pts) (B) Can the makespan be reduced by splitting the latest job? If so, by how much? (8 pts) Working Working Center 1 Center 2 Job 6 8 c 10 900 Resolution 20p HD-Ready Gateway FPD1975W TFTLCD Monitor Theft Detemce 4 8 c 10 9 e 11 7 Gateway FPD TFT LC
Five jobs are waiting for processing through two work centers. Their processing time in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Job Sigma Delta LOED> O A R-S-T-U-V OB. R-V-T-S-U OC. V-R-U-S-T OD. V-S-U-T-R O E. S-U-T-V-R
1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 a. Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 ? 2 ? 3 ? 4 ? 5 ? 6 ? b. For the schedule developed...
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...
n 10 The following set of jobs must be processed ed serially through a two-step system. The times at out of each process are in hours. If Johnson's Rule is used to sequence the jobs then Job A would complete processing on operation 2 at Job Process Process 2 A 12 9 B 11 C 7 6 D 10 14 E 5 8 Select one: A. hour 38. LO A 12 8 11 C 7 6 D 10 14 E...
Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown below Job 2 3 4 Processing Time 2 6 5 4 Due Date 10 11 15 4 13 Find a schedule that minimizes the number of tardy jobs
Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...
Each of the jobs listed in the table below must be processed first at Work Center 1 and then at Work Center 2. Use Johnson's rule to determine the sequence in which to process the jobs Job WC#1 WC#2 20 A 27 40 18 23 31 25 D 35 The first job in the sequence should be The second job in the sequence should be The third job in the sequence should be The fourth job in the sequence should...
Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...