(a) Using Johnson's algorithm,
First position will go to the job a which has shortest time with WS1
Last position will go to c which has shortest time with WS2
Second position from will go to d which has lowest time among the remaining tasks with WS1
Second last position will go to f which has lowest time with WS2 among the remaining tasks.
Third from last position will go to b which has least time with WS2.
Third position will be taken by the remaining activity, that is e.
The sequence is [ adebfc]
(b) Total makespan as shown in the chart is 54.
(c) If the last task (c) is split between WS1 and 2, in the duration of 7 and 8, with WSi and WS2 respectively will reduce the makespan by 3 days.
2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate...
Determine the processing sequence for the five jobs to be processed on the two work centers shown below using Johnson's Rule. What is the total throughput time. Show your work. Job Center1 Center2 A 6 7 B 10 9 C 12 8 D 5 11 E 13 4
please explain every step Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job Job Operation 1 (hours) 10 Operation 2 (hours) H TO For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =1 hours (enter your response as a...