Question

Using Johnsons rule for 2-machine scheduling, the sequence is: Scheduled Order Six jobs are to be processed through a two-st please explain every step
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Job

Operation 1 (hours)

Operation 2 (hours)

A

10

5

B

7

4

C

5

7

D

3

8

E

2

6

F

4

3

According to Johnson’s rule,

We will create a sequence equal to number of Jobs given.

Here we have 6 jobs. Hence the sequence will have 6 boxes.







Now, we will check the lowest operation time among all tasks and both the operations. If the Task time belongs to Operation 1, we will enter the task (or Job) from left hand side. If the task time belongs to Operation 2, we will enter the task (or Job) from right hand side. Once we enter the Job into the sequence, we will strike the Job from the list in order to avoid counting it again.

Step – 1:

The lowest operation time is 2 hours. It belongs to Operation 1 and is for Job E. We will enter Job E into the left of the sequence.

E






Now the lowest time is 3 hours. There is a tie. Operation 1 time 3 hours belongs to D and Operation 2 time 3 hours belongs to F. Hence D will be entered in Left and F in Right.

E

D




F

Now the lowest time is 4 hours. It belongs to Operation 2 for Job B. hence B will be entered to right.

E

D



B

F

Now the lowest time is 5 hours. 5 hours in Operation 1 belongs to Job C and in operation 2 belongs to A. hence C will be entered in left and A in right.

E

D

C

A

B

F

Hence the Job sequence is:

Scheduled Order

Job

1

E

2

D

3

C

4

A

5

B

6

F

Total time taken to complete all jobs:

We will make a table in order to show the time taken.


Operation 1

Operation 2

Job

Processing Time

IN

OUT

Processing Time

IN

OUT

E

2

0

2

6

2

8

D

3

2

5

8

8

16

C

5

5

10

7

16

23

A

10

10

20

5

23

28

B

7

20

27

4

28

32

F

4

27

31

3

32

35

We are writing the Job as per sequence.

For Operation – 1, E is the first Job hence will start first. As soon as Operation – 1 is free from E, it will start D. Eventually as the Operation – 1 is free from B, it will start F.

The Out time is equal to the in time plus the processing time.

In time for next Job is equal to the Out time for the previous Job.

Now we will start filling IN and OUT for Operation – 2.

We will check the operation – 1 as well as operation availability in order to start a job for Operation – 2.

Job E is done with Operation – 1 by 2nd hour. Hence Job E operation – 1 will start at 2nd hour and go till 8th hour (as processing time is 6 hours).

Now for Job D: the Operation – 1 is over at 5th hour, but Operation – 2 has been freed from Job E at 8th hour. Hence the Job D will start at 8th hour and go till 16 hours.

Similarly, if operation – 2 is free when a job is done with Operation – 1, the job will start immediately with Operation – 2. But if Operation – 2 is not free, then the job will wait till Operation – 2 is free and then will start.

Hence for Operation – 2 the start time can be mention as: MAX(OUT time of previous task in operation – 2, Out time of same task in operation – 1).

Here, the total time taken = 35 hours.


answered by: ANURANJAN SARSAM
Add a comment
Answer #2

Job

Operation 1 (hours)

Operation 2 (hours)

A

10

5

B

7

4

C

5

7

D

3

8

E

2

6

F

4

3

According to Johnson’s rule,

We will create a sequence equal to number of Jobs given.

Here we have 6 jobs. Hence the sequence will have 6 boxes.

Now, we will check the lowest operation time among all tasks and both the operations. If the Task time belongs to Operation 1, we will enter the task (or Job) from left hand side. If the task time belongs to Operation 2, we will enter the task (or Job) from right hand side. Once we enter the Job into the sequence, we will strike the Job from the list in order to avoid counting it again.

Step – 1:

The lowest operation time is 2 hours. It belongs to Operation 1 and is for Job E. We will enter Job E into the left of the sequence.

E

Now the lowest time is 3 hours. There is a tie. Operation 1 time 3 hours belongs to D and Operation 2 time 3 hours belongs to F. Hence D will be entered in Left and F in Right.

E

D

F

Now the lowest time is 4 hours. It belongs to Operation 2 for Job B. hence B will be entered to right.

E

D

B

F

Now the lowest time is 5 hours. 5 hours in Operation 1 belongs to Job C and in operation 2 belongs to A. hence C will be entered in left and A in right.

E

D

C

A

B

F

Hence the Job sequence is:

Scheduled Order

Job

1

E

2

D

3

C

4

A

5

B

6

F

Total time taken to complete all jobs:

We will make a table in order to show the time taken.

Operation 1

Operation 2

Job

Processing Time

IN

OUT

Processing Time

IN

OUT

E

2

0

2

6

2

8

D

3

2

5

8

8

16

C

5

5

10

7

16

23

A

10

10

20

5

23

28

B

7

20

27

4

28

32

F

4

27

31

3

32

35

We are writing the Job as per sequence.

For Operation – 1, E is the first Job hence will start first. As soon as Operation – 1 is free from E, it will start D. Eventually as the Operation – 1 is free from B, it will start F.

The Out time is equal to the in time plus the processing time.

In time for next Job is equal to the Out time for the previous Job.

Now we will start filling IN and OUT for Operation – 2.

We will check the operation – 1 as well as operation availability in order to start a job for Operation – 2.

Job E is done with Operation – 1 by 2nd hour. Hence Job E operation – 1 will start at 2nd hour and go till 8th hour (as processing time is 6 hours).

Now for Job D: the Operation – 1 is over at 5th hour, but Operation – 2 has been freed from Job E at 8th hour. Hence the Job D will start at 8th hour and go till 16 hours.

Similarly, if operation – 2 is free when a job is done with Operation – 1, the job will start immediately with Operation – 2. But if Operation – 2 is not free, then the job will wait till Operation – 2 is free and then will start.

Hence for Operation – 2 the start time can be mention as: MAX(OUT time of previous task in operation – 2, Out time of same task in operation – 1).

Here, the total time taken = 35 hours.

.

.

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!

Add a comment
Know the answer?
Add Answer to:
please explain every step Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Six...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and...

    Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and the second involves painting. Processing times are as​ follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 a. Using​ Johnson's rule for​ 2-machine scheduling, the sequence​ is: Scheduled Order Job 1 ? 2 ? 3 ? 4 ? 5 ? 6 ? b. For the schedule developed...

  • Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...

    Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...

  • 2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate...

    2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate total throughput (makespan) time. (12 pts) (B) Can the makespan be reduced by splitting the latest job? If so, by how much? (8 pts) Working Working Center 1 Center 2 Job 6 8 c 10 900 Resolution 20p HD-Ready Gateway FPD1975W TFTLCD Monitor Theft Detemce 4 8 c 10 9 e 11 7 Gateway FPD TFT LC

  • Question 2 3 pts Per Johnson's rule - If a job has to go through two...

    Question 2 3 pts Per Johnson's rule - If a job has to go through two machines: First for 3 hours on Welding and then 4 hours on Painting - and if the 3 hours was the shortest processing time of all jobs going through these operations, I would: Schedule this job as late as possible Schedule this job as early as possible

  • please answer this ABC's machine shop is considering the use of priority scheduling rule in the...

    please answer this ABC's machine shop is considering the use of priority scheduling rule in the fabrication shop and must decide whether to use: a. Critical ratio (CR) Earliest due date (EDD) C. Shortest operation next (SON)/Shortest processing time 9SPT) d. Order Slack Order No. Total Remaining Time Remaining Current operation Manufacturing until Due Date Processing time Time (days) (days) (days) А 12 15 10 14 D 18 15 19 Using the four sequencing rules, compute the scheduling priority for...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT