Problem 2 (6 points):

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):

Job

Processing Time (Days)

Due Date

(days from Now)

A

2

2

B

5

6

C

6

10

D

9

6

E

4

8

What is the average flow time for the shortest processing time (SPT) rule schedule?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Shortest processing time (SPT): Priority rule that gives top priority to the waiting job whose operation time at a work centers is shortest

Jobs are processed by Shortest processing time (SPT) rule where job with shortest processing time processed first and job with longest processing time processed last

                                                   

Job

Processing time (days)

Due date

Flow Time (Cumulative processing Time)

A

2

2

2

E

4

8

6

B

5

6

11

C

6

10

17

D

9

6

26

Total

26

62

Average flow time = Total flow time/ number of jobs = 62/5 = 12.4 days

Add a comment
Know the answer?
Add Answer to:
Problem 2 (6 points): Refer to the following data for jobs waiting to be processed at...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and...

    Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and times are expressed in terms of hours. All pertinent data are given in the following table. Job Time Since Job Arrived Processing Time Due Date A 8 3 10 B 7 6 14 C 6 3 2 D 4 2 6 E 1 5 16 Using the information in the Table and the SPT rule, what is the average flow time? Fewer than or...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • 1. Five jobs are waiting to be processed. Their processing times and due dates are given...

    1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • The following jobs are waiting to be processed at Rick Carlson’s machine center.

    15.13 The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and sets fresh schedulesevery 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers.Job Date Job Received Production Days Needed Date Job DueBR-02 228...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT