What would be the sequence of the following jobs if you did them in Earliest Due Date sequence? Job A B Processing Time Days
Question 6 (10 points) You have 5 jobs to do. What would be the sequence if you chose to do a Shortest Processing Time Approa
Question 7 (10 points) If you have 5 jobs and you do not change the sequence, what will be the average flowtime for all 5 job
be the Average Tardiness for these 5 jobs if you did them in Shortest Processing Time sequence? Job А B Processing Time Days
What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead
0 0
Add a comment Improve this question Transcribed image text
Answer #1

My dear student as per HomeworkLib policy i am allowed to solve one question at a time so I am solving the first question in the pic. Thank you

of do earliest deure date Bequence Reb alue dlate C 10 D 12 n 16 A 24 E 30 so Sequence js с D 3 A E options С

Add a comment
Know the answer?
Add Answer to:
What would be the sequence of the following jobs if you did them in Earliest Due...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have 5 jobs to process. If you process them in the current order, what will...

    You have 5 jobs to process. If you process them in the current order, what will be the average tardiness for the five jobs? Job А Processing Time Days Due from Today 16 24 20 16 22 40 12 17 10 с D E 18 26.4 28.0 35.4 30.6 23.2

  • Question 7 (10 points) What would be the sequence of the following jobs if you did...

    Question 7 (10 points) What would be the sequence of the following jobs if you did them in Earliest Due Date sequence? Job Processing Time Days Due from Today 34 A 16 B 23 41 40 22 14 28 E 20 18 E,A,D,B,C E,D,A,C,B C,D,B,A,E C,B,D,A,E U Lu

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • What would be the change in Average Tardiness if you performed the following five tasks using...

    What would be the change in Average Tardiness if you performed the following five tasks using Earliest Delivery Date instead of completing them in the current sequence? Job Processing Time Days Due from Today Lowers average tardiness by 9.0 Lowers average tardiness by 6.6 Lowers average tardiness by 7.2 Lowers average tardiness by 11.6 Lowers average tardiness by 7.0

  • You have 5 jobs to process. What is the makespan if you do them in the...

    You have 5 jobs to process. What is the makespan if you do them in the current order? Job А B с D Processing Time Days Due from Today 16 24 20 16 22 40 12 17 10 18 70 83 79 89 80

  • The following table contains information concerning four jobs that are awaiting processing at a work center....

    The following table contains information concerning four jobs that are awaiting processing at a work center. Job Job Time (Days) Due Date (Days) A 14 20 B 10 16 C 7 15 D 6 17 a. Sequence the jobs using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. Assume the list is by order of arrival. Sequence for First come, first served   (Click to select)   A-B-C-D   D-C-B-A   C-B-D-A   A-C-D-B Sequence for Shortest processing time   (Click...

  • Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours...

    Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours) (Hours) Job 3.5 2.0 4.5 5.0 2.5 6.0 18 20 Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. a-1. Sequence for First come, first served (Click to select) Sequence for Shortest processing time Click to select) Sequence for Earliest due date (Click to select) Click to select) Sequence...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • Job А 3. The jobs listed below needed to be completed. Assume that it is now...

    Job А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Processing Time (days) Due Date 20 180 30 200 10 175 230 210 B с D 16 18 E If the jobs are sequenced according to shortest processing time rule, what is the average completion time? A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to the longest...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT