If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness...

If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness (in days) is (assume zero for today's date)

Job

Processing Time (days)

Due Date

A

8

12

B

6

15

C

11

17

D

7

10

E

3

8

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A F 1 Job B с D Processing Time (days) Due Date Slack 7 10 E Flow time Tradiness 7 0 15 3 2 D 3 3 A 3 12 4 4 E 3 8 5 18 10 5

Maximum job tardiness is 20 days

FOrmula

A B C D F 1 Job Processing Time (days) Due Date 2 D 7 10 3 A 8 12 Slack =C2-B2 =C3-B3 =C4-B4 =C5-B5 =C6-B6 E Flow time -SUM(B

Add a comment
Know the answer?
Add Answer to:
If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • What would be the sequence of the following jobs if you did them in Earliest Due...

    What would be the sequence of the following jobs if you did them in Earliest Due Date sequence? Job A B Processing Time Days Due from Today 18 24 16 16 26 10 14 12 21 30 С D E OE,A,D,B,C E,D,A,C,B OC,D,B,A,E, C.B.D.A,E Question 6 (10 points) You have 5 jobs to do. What would be the sequence if you chose to do a Shortest Processing Time Approach? Job Processing Time Days Due from Today А 24 30 B...

  • Job А 3. The jobs listed below needed to be completed. Assume that it is now...

    Job А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Processing Time (days) Due Date 20 180 30 200 10 175 230 210 B с D 16 18 E If the jobs are sequenced according to shortest processing time rule, what is the average completion time? A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to the longest...

  • # A 3. The jobs listed below needed to be completed. Assume that it is now...

    # A 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 180 30 с 10 175 16 230 E 18 210 B 200 D 1:54 If the jobs are sequenced according to shortest processing time rule, what is the average completion time! A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to...

  • Given the following set of jobs waiting to run on a machine, use the Slack (least...

    Given the following set of jobs waiting to run on a machine, use the Slack (least slack time remaining) dispatching rule to sequence the jobs. Job Days Until Due Date Processing Time A 35 30 B 27 17 C 33 30 D 41 25 A. A,B,C,D B. B,C,D,A C. C,A,B,D D. B,C,A,D E. none of the above

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Determine the processing sequence that would result using the Slack per operation rule. Given the information...

    Determine the processing sequence that would result using the Slack per operation rule. Given the information in the following table Remaining Number of Job Time (Days) Due Date Operations Remaining Processing 8 6 10 12 10 8 Determine the processing sequence that would result using the Slack per operation rule. The sequence is (Click to select) v

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38...

    Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e., if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness of...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • The jobs listed below need to be completed. Assume that it is now day 140. If...

    The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time​ rule, what is the lateness of job​ A? Job Processing Time​ (days) Job due date​ (days) A 20 180 B 30 200 C 10 175 D 16 230 E 18 210 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 140. Assume each job starts at the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT