Question

# A 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 18

0 0
Add a comment Improve this question Transcribed image text
Answer #1

3)

Considering that jobs are started on day 140, so day 140 is the first working day for these jobs.

F A B с D E 1_3) Shortest Processing Time rule Jobs are scheduled in ascending order of their processig time 2 3 4 Starting d

EXCEL FORMULA:

F А В с D E 1 3 Shortest Processing Time rule 2 Jobs are scheduled in ascending order of their processig time 3 4 Starting da

Average completion time:  A. 47.6

-----------------------------------------------------

4)

Schedule based on longest processing time rule, is following:

F G 1 A B с D E 3 Longest Processing Time rule Jobs are scheduled in descending order of their processig time 2 3 4 Starting

EXCEL FORMULAS remain same as for part (3)

Lateness of job B = D. 9

Add a comment
Know the answer?
Add Answer to:
# A 3. The jobs listed below needed to be completed. Assume that it is now...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job А 3. The jobs listed below needed to be completed. Assume that it is now...

    Job А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Processing Time (days) Due Date 20 180 30 200 10 175 230 210 B с D 16 18 E If the jobs are sequenced according to shortest processing time rule, what is the average completion time? A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to the longest...

  • А 3. The jobs listed below needed to be completed. Assume that it is now day...

    А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 180 30 200 10 175 16 230 18 210 B с D E 4. Given the data from question 3, if the jobs are sequenced according to the longest processing time rule, what is the lateness of job B? A. O B. 24 C. 7.4 D. 9 E 13.4 5. If it takes 60 hours to...

  • The jobs listed below need to be completed. Assume that it is now day 140. If...

    The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time​ rule, what is the lateness of job​ A? Job Processing Time​ (days) Job due date​ (days) A 20 180 B 30 200 C 10 175 D 16 230 E 18 210 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 140. Assume each job starts at the...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Five jobs are ready for processing at time zero through a workstation. The details regarding the...

    Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table. Job Processing Time (days) Days Due from Today A6 C 5 Using the shortest processing time (SPT) rule, it can be concluded that the average lateness for the five jobs is: O a. more than -6 but less than or equal to -2 days. O b. more than -2 but...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • 4. [10 points] Today is Nov 15. The following jobs need to be scheduled on the...

    4. [10 points] Today is Nov 15. The following jobs need to be scheduled on the same machine. Job Processing Time (Davs) Due Date Nov 30 Dec 22 Nov 18 Dec 3 Nov 29 12 a. Schedule the jobs according to i. Shortest processing time ii. Earliest due date. iii. Longest processing time. b. For the SPT& EED schedules from part a, calculate the average completion time.

  • If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness...

    If the following jobs are sequenced according to the SLACK rule then the maximum job tardiness (in days) is (assume zero for today's date) Job Processing Time (days) Due Date A 8 12 B 6 15 C 11 17 D 7 10 E 3 8

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT