The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time rule, what is the lateness of job A?
Job |
Processing Time (days) |
Job due date (days) |
A |
20 |
180 |
B |
30 |
200 |
C |
10 |
175 |
D |
16 |
230 |
E |
18 |
210 |
All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 140. Assume each job starts at the beginning of the day and finishes at the end of the day (a job that begins on day 140 and takes 8 days will finish on day 147, and the next job begins in the morning of day 148). Compute all times based on initiating work on day 140.
A.
0.0 days
B.
7.4 days
C.
24.0 days
D.
9.0 days
E.
11.6 days
As per the longest processing time, we will process B first. It will start on the day 140 and end on day 169 (30 days).
A then starts on Day 170 and takes 20 days and ends on Day 189.
JoB A Latesness = 189 - 180 = 9 days
The jobs listed below need to be completed. Assume that it is now day 140. If...
# A 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 180 30 с 10 175 16 230 E 18 210 B 200 D 1:54 If the jobs are sequenced according to shortest processing time rule, what is the average completion time! A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to...
А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 180 30 200 10 175 16 230 18 210 B с D E 4. Given the data from question 3, if the jobs are sequenced according to the longest processing time rule, what is the lateness of job B? A. O B. 24 C. 7.4 D. 9 E 13.4 5. If it takes 60 hours to...
Job А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Processing Time (days) Due Date 20 180 30 200 10 175 230 210 B с D 16 18 E If the jobs are sequenced according to shortest processing time rule, what is the average completion time? A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to the longest...
a) Using the FCFS (first come, first
served ) decision rule for sequencing the jobs, the order is
(assume that jobs came in the order in which they are listed in
the table):
Sequence
Job
1
A
2
B
3
C
4
D
5
E
The average tardiness (job lateness) for the sequence developed
using the FCFS rule = ___ days (round your response to two
decimal places).
The following jobs are waiting to be processed at the same
machine...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
The following jobs are waiting to be processed at a small machine center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...
a) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule = nothing...
Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...
The following jobs are waiting to be processed at a small machine center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...