Question

А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 1804. Given the data from question 3, if the jobs are sequenced according to the longest processing time rule, what is the laten

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Question 4: A.0

Job B has the longest processing time so it will be scheduled first,

Completion time for Job B = 139 + Processing time = 139 + 30 = 169

Lateness = Max (0, Completion time - Due date) = 0

Question 5: A. 95.04%

T1 = 60

T12 = 50

Tn = T1*(n)^b

Where b = learning index

T12 = T1* (12)^b

50 = 60*12^b

12^b = 50/60

b*LN(12) = LN(50/60)

b = -0.07337

b = LN(R) / LN(2)

Where R = Learning Rate

-0.07337*LN(2) = LN(R)

LN(R) = -0.050857

R = e^-0.050857

R = 0.9504 = 95.04%

Add a comment
Know the answer?
Add Answer to:
А 3. The jobs listed below needed to be completed. Assume that it is now day...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job А 3. The jobs listed below needed to be completed. Assume that it is now...

    Job А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Processing Time (days) Due Date 20 180 30 200 10 175 230 210 B с D 16 18 E If the jobs are sequenced according to shortest processing time rule, what is the average completion time? A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to the longest...

  • # A 3. The jobs listed below needed to be completed. Assume that it is now...

    # A 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 180 30 с 10 175 16 230 E 18 210 B 200 D 1:54 If the jobs are sequenced according to shortest processing time rule, what is the average completion time! A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to...

  • The jobs listed below need to be completed. Assume that it is now day 140. If...

    The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time​ rule, what is the lateness of job​ A? Job Processing Time​ (days) Job due date​ (days) A 20 180 B 30 200 C 10 175 D 16 230 E 18 210 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 140. Assume each job starts at the...

  • 6. If it took 80 hours to produce the first unit of a product, and the...

    6. If it took 80 hours to produce the first unit of a product, and the learning rate is 80%, how long will it take to produce units 26 through 125? A. 1158.54 hours B. 1998.94 hours C. 1779.07 hours D. 2064.36 hours E Impossible to answer in the time allowed. 5. If it takes 60 hours to produce the first unit of a product and 50 hours to produce the 12th unit, what is the learning rate? A. 95.04%...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Five jobs are waiting to be processed. Their processing times and due dates are given below....

    Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and...

    Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and times are expressed in terms of hours. All pertinent data are given in the following table. Job Time Since Job Arrived Processing Time Due Date A 8 3 10 B 7 6 14 C 6 3 2 D 4 2 6 E 1 5 16 Using the information in the Table and the SPT rule, what is the average flow time? Fewer than or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT