Question

% Problem 15.15 a) Using the FCFS (first come, first served ) decision rule for sequencing the jobs, the order is (assume tha: Question Help The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: Jo%x Problem 15.15 Question Help a) Using the FCFS (first come first served ) decision rule for sequencing the jobs, the ordera) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the order is​ (assume that jobs came in the order in which they are listed in the​ table):

Sequence

Job

1

A

2

B

3

C

4

D

5

E

The average tardiness​ (job lateness) for the sequence developed using the FCFS rule​ = ___ days ​(round your response to two decimal​ places).

The following jobs are waiting to be processed at the same machine center. Jobs are logged as they​ arrive:

                                                                             

Job

Due Date

Duration​ (days)

A

315

3

B

313

8

C

312

16

D

325

40

E

314

5

All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day​ (a job that begins on day 275 and takes 8 days will finish on day​ 282, and the next job begins in the morning of day​ 283). Compute all times based on initiating work on day 275.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a) FCFS sequence:
Sequence Job
1 A
2 B
3 C
4 D
5 E
DAY OF ARRIVAL 275
Sequence Job Due Date Duration (days) Arrival Date Completion Date job lateness
1 A 315 3 275 278 0
2 B 313 8 275 286 0
3 C 312 16 275 302 0
4 D 325 40 275 342 17
5 E 314 5 275 347 33
Note: Tardiness or lateness is the number of days after the due date that the job takes to complete.
Average lateness 10.00
the average tardiness for the sequence developed using the FCFS rule = 10.00 days

formula used:

C D E F 2 3 Job Duration (days) Due Date 315 313 COUW 312 325 314 10 a) FCFS sequence: 11 Sequence 12 1 13 2 14 3 154 16 5 17

Add a comment
Know the answer?
Add Answer to:
a) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...

    Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing...

    Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be prooessed at Rick Sclano's machine center. Solanos machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

  • The jobs listed below need to be completed. Assume that it is now day 140. If...

    The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time​ rule, what is the lateness of job​ A? Job Processing Time​ (days) Job due date​ (days) A 20 180 B 30 200 C 10 175 D 16 230 E 18 210 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 140. Assume each job starts at the...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT