Based on First Come First Served, we get the sequence as A-B-C-D-E
We find the Average flow time and Average days past due based on FCFS as shown below:
Based on the Earliest due date, we get the sequence as B-D-C-A-E
We find the Average flow time and Average days past due based on EDD as shown below:
As seen from above, the earliest due date sequence gives the best schedule as both Average flow time and Average days due are less as compared to FCFS sequence.
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!
Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro-...
Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 6 18 66 B 3 24 58 C 2 32 80 D 10 22 26 E 8 12 50 Create a schedule using the first-come first-serve (FCFS) rule, calculating the average...
Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago) (hours from now) Order 1 0 2* 10 12 3 5 8 3 18 20 The due dates reflect the need for the order to be hours t its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due Using the FCFS (first come, first served) decision rule...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job. Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9 Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...
The following jobs are waiting to be processed at a small machine center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...
Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...
The following jobs are waiting to be processed at a small machine center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...
Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. JOB DUE DATE (HOURS...