Question

Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The...

Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The time since the order​ arrived, processing​ time, and promised due dates are given in the following table.

Job

Time Since Order Arrived

(days ago)

Processing Time

(days)

Due Date

(days from now)

A

6

18

66

B

3

24

58

C

2

32

80

D

10

22

26

E

8

12

50

  1. Create a schedule using the first-come first-serve (FCFS) rule, calculating the average flow time and average days past due.
  2. Create a schedule using the earliest due date (EDD) rule, calculating the average flow time and average days past due.
  3. Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.

Schedule using first-come first-serve (FCFS) rule :

Arrange jobs in their arrival order chronologically ,

which would be D, E, A, B, C as per time since order arrived in days ago, in the table given

Now the table below provides the Schedule using FCFS :

Job

Time Since Order Arrived

(days ago)

Start time

Processing Time

(days)

End Time

(= Start Time + Processing Time)

Flow TIme

(= TIme Since order Arrived +End Time)

Due Date

(days from now)

Days Past Due

(= End Time - Due Date ; when End Time > Due Date else 0 )

D 10 0 22 22 32 26 0
E 8 22 12 34 42 50 0
A 6 34 18 52 58 66 0
B 3 52 24 76 79 58 22
C 2 76 32 108 110 80 28

All the bold lettered columns in above table are taken directly from the given table and the rest columns values are calculated as per equation given which is self explanatory.

Average Flow time = (32 + 42 + 58 + 79 +110 ) / 5 = 321 / 5 = 62.5

Average Days Past Due = ( 0 + 0 + 0 +22 + 28) / 5 = 50 / 5 = 10

b.

Schedule using earliest due date (EDD) rule :

Arrange jobs in their earliest due date chronologically ,

which is D, E, B, A, C as per due date, in the table given

Now the table below provides the Schedule using EDD :

Job

Time Since Order Arrived

(days ago)

Start time

Processing Time

(days)

End Time

(= Start Time + Processing Time)

Flow TIme

(= TIme Since order Arrived + End Time)

Due Date

(days from now)

Days Past Due

(= End Time - Due Date ; when End Time > Due Date else 0 )

D 10 0 22 22 32 26 0
E 8 22 12 34 42 50 0
B 3 34 24 58 61 58 0
A 6 58 18 76 82 66 10
C 2 76 32 108 110 80 28

All the bold lettered columns in above table are taken directly from the given table and the rest column values are calculated as per equation given which is self explanatory.

Average Flow Time = (32 + 42 + 61 + 81 + 110) / 5 = 326 / 5 = 65.2

Average Days Past Due = ( 0 + 0 + 0 + 10 + 28 ) / 5 = 38 / 5 = 7.6

c.

We can see

Average Flow Time in FCFS = 62.5 is lesser than in EDD = 65.2

This makes sense , as in FCFS schedule, one prioritises to finish the tasks arrived earlier which in turn improves the Total Flow Time, and hence we find better Average Flow Time.

Average Days Past Due in EDD = 7.6 is lesser than in FCFS = 10

This makes sense , as in EDD schedule, one prioritises to finish the tasks which have earlier due dates, which in turn improves the Total Days Past Due, and hence we find better Average Days Past Due.

Add a comment
Know the answer?
Add Answer to:
Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro-...

    Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro- cessed as of 8 A.M. today (day 23) at its bottleneck opera- tion. The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Job А 11 10 22 10 8 В 13 8...

  • Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago)...

    Problem 18 Question Help Estimated Machine Time (hours) Time Since Order Due Date Arrived (hours ago) (hours from now) Order 1 0 2* 10 12 3 5 8 3 18 20 The due dates reflect the need for the order to be hours t its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due Using the FCFS (first come, first served) decision rule...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...

    Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 6 18 B 3 14 C 4 9 D 5 19 E 2 11 Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____. a. more than 10 but less than or equal to 12 days....

  • please answer this ABC's machine shop is considering the use of priority scheduling rule in the...

    please answer this ABC's machine shop is considering the use of priority scheduling rule in the fabrication shop and must decide whether to use: a. Critical ratio (CR) Earliest due date (EDD) C. Shortest operation next (SON)/Shortest processing time 9SPT) d. Order Slack Order No. Total Remaining Time Remaining Current operation Manufacturing until Due Date Processing time Time (days) (days) (days) А 12 15 10 14 D 18 15 19 Using the four sequencing rules, compute the scheduling priority for...

  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT