Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 6 18 B 3 14 C 4 9 D 5 19 E 2 11 Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____. a. more than 10 but less than or equal to 12 days. b. more than 8 but less than or equal to 10 days. c. more than 12 but less than or equal to 14 days. d. more than 14 but less than or equal to 16 days.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

According to the EDD rule the jobs are processed in order of their due date of completion. This means the job having the earliest due date is processed first and so on

In this problem job c has the earliest due date of 9 so it is proceesed first, the second is E with due date of 11,third is B with due date of 14,fourth is A with due date of 18 and last is D with due date of 19

So using the EDD rule the sequence of the job is C-E-B-A-D

Then we have to calculate the flow time of each job according to the sequence. Flow time = cumulative sum of the processing time

Job processing time flow time

C 4 4

E 2 6 (as 4+2 = 6)

B 3 9 (as 6+3 = 9)

A 6 15 (as 9+6 = 15)

D 5 20 (as 15+5 = 20)

Average flow time = sum of the flow time for each job/number of jobs

= (4+6+9+15+20) /5

= 54/5

= 10.8

So the answer is option a i. e more than 10 but less than or equal to 12 days

Add a comment
Know the answer?
Add Answer to:
Five jobs are ready for processing at time zero through a workstation. The details of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date (days) A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is: a. more than -6 but less than or equal to -2 days. b....

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 8 12 B 4 9 C 3 6 D 7 7 E 5 20 Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____. a. more than 14 but less than...

  • Five jobs are ready for processing at time zero through a workstation. The details regarding the...

    Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table. Job Processing Time (days) Days Due from Today A6 C 5 Using the shortest processing time (SPT) rule, it can be concluded that the average lateness for the five jobs is: O a. more than -6 but less than or equal to -2 days. O b. more than -2 but...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and...

    Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and times are expressed in terms of hours. All pertinent data are given in the following table. Job Time Since Job Arrived Processing Time Due Date A 8 3 10 B 7 6 14 C 6 3 2 D 4 2 6 E 1 5 16 Using the information in the Table and the SPT rule, what is the average flow time? Fewer than or...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Processing times and due dates for five jobs are shown in the table below. Assume the...

    Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) 3 556 3 12. What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? (0.10...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The...

    Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The time since the order​ arrived, processing​ time, and promised due dates are given in the following table. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 6 18 66 B 3 24 58 C 2 32 80 D 10 22 26 E 8 12 50 Create a schedule using the first-come first-serve (FCFS) rule, calculating the average...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT