Question

Part 3 a. From the information in part 1, estimate the production in ccy per hour for a roller if its average speed will be 5

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q. A12 > Given, Avg. speed, S = 5 mph Compacted width Per pass, w = 5.5 ft. Lift thickness, L= 8 No. of passes, N= 5 Efficie

Add a comment
Know the answer?
Add Answer to:
Part 3 a. From the information in part 1, estimate the production in ccy per hour...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a) Estimate the production in compacted cubic yards per hour for a roller if its average...

    a) Estimate the production in compacted cubic yards per hour for a roller if its average speed will be 9.5 mph and it will cover 6.7 ft in one pass. The job specifications limit the compacted lift thickness to 4.8 inches and require 7 passes per lift. The company usually figures production based on 45 min per hour. b) How many hours will you need to produce 28,364 compacted cubic yards using this equipment (using the productivity from part(a)? C)...

  • Part 2 Based upon the results to part 1, the project requires hauling materials to, or...

    Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...

  • Part 2 Based upon the results to part 1, the project requires hauling materials to, or...

    Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...

  • use following to solve 3) Using an order of magnitude method (Hill), estimate the TCI in...

    use following to solve 3) Using an order of magnitude method (Hill), estimate the TCI in year 2006 dollars for a grass-roots plant with 100,000-lb annual production using an order-of-magnitude method based on a 10,000-lb annual production. The plant contains three 1200-ft/min centrifugal fans, five 1500-ft/min centrifugal blowers, seven 100-ft' centrifugal separators, and two 100-ft shell-and-tube heat exchangers. You may assume all materials are carbon steel, the materials handled are primarily solid, and that this plant construction is done fully...

  • Check my work Required information The following information applies to the questions displayed below.) Part 1...

    Check my work Required information The following information applies to the questions displayed below.) Part 1 of 5 128 Kitchen King's Toledo plant manufactures three product lines, all multi-burner, ceramic cook tops. The plant's three product models are the Regular (REG), the Advanced (ADV), and the Gourmet (GMT). Until recently, the plant used a job-order product-costing system, with manufacturing overhead applied on the basis of direct-labor hours. The following table displays the basic data upon which the traditional costing system...

  • summarizr the followung info and write them in your own words and break them into different...

    summarizr the followung info and write them in your own words and break them into different key points.   6.5 Metering Chamber: 6.5.1 The minimum size of the metering box is governed by the metering area required to obtain a representative test area for the specimen (see 7.2) and for maintenance of reasonable test accuracy. For example, for specimens incorporating air spaces or stud spaces, the metering area shall span an integral number of spaces (see 5.5). The depth of...

  • summatize the following info and break them into differeng key points. write them in yojr own...

    summatize the following info and break them into differeng key points. write them in yojr own words   apartus 6.1 Introduction—The design of a successful hot box appa- ratus is influenced by many factors. Before beginning the design of an apparatus meeting this standard, the designer shall review the discussion on the limitations and accuracy, Section 13, discussions of the energy flows in a hot box, Annex A2, the metering box wall loss flow, Annex A3, and flanking loss, Annex...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework