a) given,
speed of the roller = 9.5mph
width it will cover in one pass = 6.7ft
thickness of lift = 4.8inch = 0.4ft
Number of passes required per lift = 7
Therefore distance travelled in 1 hour(45 minutes) = 9.5*(45/60) = 7.125miles
Since 7 passes are required per lift, distance covered =7.125/7 =1.018miles = (1.018*5280) ft =5375.04 ft
production per hour(45 minutes) for roller = 5375.04*6.7*0.4 = 14405.11 cub ft = (14405.11*0.037037) cub yard =533.52 cubic yard
b)
Time required to compact 28,364 cubic yard = 28,364/533.52 = 53.16 hours
c) given,
speed of the pneumatic roller = 12mph
width it will cover in one pass = 7.1ft
thickness of lift = 6.5inch = 0.54 ft
Number of passes required per lift = 9
Therefore distance travelled in 1 hour(51 minutes) = 12*(51/60) = 10.2 miles
Since 9 passes are required per lift, distance covered =10.2/9 =1.13miles = (1.13*5280) ft =5984 ft
production per hour(51 minutes) for roller = 5984*7.1*0.54 = 22942.65 cub ft = (22942.65*0.037037) cub yard =849.73 cubic yard
**********If this work helped you, please give a thumbs up and support us. Thank you*********
a) Estimate the production in compacted cubic yards per hour for a roller if its average...
Part 3 a. From the information in part 1, estimate the production in ccy per hour for a roller if its average speed will be 5 mph and it will cover 5.5 ft in one pass. The job specifications limit the compacted lift thickness to 8" and require five passes per lift. Figure production based upon a 55-min hour. b. Determine the total time required to complete compacation work on the site.
Earth soil is being delivered to an embankment at a rate of 2000 lcy/hr. The compaction process is being done using rollers with a drum width of 4.16 ft. The recommended compacted lift height is 7 inches with 4 drum passes at a speed of 2 mph. With an assumption of 55 min/hour efficiency, determine the number of rollers required to provide the necessary compaction for the delivered soil. Assume that lifts are placed at 10-in thickness before compaction for...
9.10 For each of the stated conditions, determine the probable production expressed in cubic yards per hour bank measure for a shovel equipped with a 5-cy bucket. The shovel has a maximum digging height of 34 ft. Use a 50-min-hour efficiency factor but be aggressive with the assumed fill factor. Class of material Shot rock, poorly blasted Shot rock, well blasted Condition Height of excavation (ft) 23.8 17 Angle of swing (degrees) 75 120 Loading haul units yes yes
Your company is planning to bid a contract to lay 60,000 square yards of asphalt pavement to improve the Carolinas airport runway. You have been asked to estimate the duration and direct equipment cost of the project. The contract specifications require that the pavement be 3 inches thick after compaction. The mix design is such that you estimate the asphalt to weigh 3,100 pounds per cubic yard when loose and 3,900 pounds per cubic yard after it has been compacted....