Question

A complete flexible budget performance report: Multiple Choice would be the same as a planning budget report. 0 must be prepa

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is "would be based on actual activity for the period covered".

Supporting explanations:

A flexible budget performance report is prepared to compare the actual results for a particular period with the flexible budget performance results in order to know how the performance for that particular period.

Therefore, the correct answer is "would be based on actual activity for the period covered.

Add a comment
Know the answer?
Add Answer to:
A complete flexible budget performance report: Multiple Choice would be the same as a planning budget...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1)Which of the following may appear on a flexible budget performance report? Multiple Choice An unfavorable...

    1)Which of the following may appear on a flexible budget performance report? Multiple Choice An unfavorable spending variance. A favorable revenue variance. An unfavorable activity variance. All of the above may appear on a flexible budget performance report. 2) Rients Corporation is a service company that measures its output by the number of customers served. The company has provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results of operations for October....

  • Which of the following may appear on a flexible budget performance report? Multiple Choice A favorable...

    Which of the following may appear on a flexible budget performance report? Multiple Choice A favorable revenue variance . An unfavorable spending variance . An unfavorable activity variance . All of the above may appear on a flexible budget performance report.

  • Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance...

    Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget 9.530 Activity Variances Planning Budget 9,050 Labor-hours (9) 5 159,305 $ 157,245 20,812 2,206 F 1,500 U 57.000 Direct labor Indirect labor Utilities Supplies Equipment depreciation 1.409) g) ) 17,860 4350 + 5.010 0 None None 79,650 Factory administration 18 800 + $ 1.40 ) $313.4597 Total expense

  • Hoppy Corporation compares a monthly flexible budget based on actual operating results to a static planning...

    Hoppy Corporation compares a monthly flexible budget based on actual operating results to a static planning budget prepared at the beginning of the month. When the actual level of activity is higher than expected, which of the following would typically be expected? Variable costs would show unfavorable variances O Varíable costs would show favorable variances O Fixed costs would show favorable varlances Fixed costs would show unfavorable variances. None of the above. Cosden Corporation is an oil well service company...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget...

  • Sunshine Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate...

    Sunshine Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Results Spending Variances Flexible Budget Activity Variances Planning Budget Labor-hours (q) 9,550 9,070 Direct labor ( q) $169,205 $167,125 Indirect...

  • Ray Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department’s Flexible Budget Performance Report. Ray Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate per hour" answers to...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour answers to 2 decimal places. Indicate the effect of each varlance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (I.e., zero varlance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour answers to 2 decimal places. Indicate the effect of each varlance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (I.e., zero varlance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Spending Variances Results Budget...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT