Which of the following may appear on a flexible budget performance report? Multiple Choice A favorable...

Which of the following may appear on a flexible budget performance report?

Multiple Choice

A favorable revenue variance

. An unfavorable spending variance

. An unfavorable activity variance

. All of the above may appear on a flexible budget performance report.

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Answer:

All of the above may appear on a flexible budget performance report.

It is because by preparing the flexible budget performance report the manger can prepare the report by isolating the Revenue, spending and the activity variance.So; all these three will appear in the flexible budget.

Add a comment
Know the answer?
Add Answer to:
Which of the following may appear on a flexible budget performance report? Multiple Choice A favorable...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • 1)Which of the following may appear on a flexible budget performance report? Multiple Choice An unfavorable...

    1)Which of the following may appear on a flexible budget performance report? Multiple Choice An unfavorable spending variance. A favorable revenue variance. An unfavorable activity variance. All of the above may appear on a flexible budget performance report. 2) Rients Corporation is a service company that measures its output by the number of customers served. The company has provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results of operations for October....

  • Ray Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department’s Flexible Budget Performance Report. Ray Company provided the following excerpts from its Production Department’s flexible budget performance report. (Round "rate per hour" answers to...

  • Required: Prepare a flexible budget performance report that shows the company's revenue and spending variances and...

    Required: Prepare a flexible budget performance report that shows the company's revenue and spending variances and activity variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Lavage Rapide Flexible Budget Performance Report For the Month Ended August 31 Actual Results 8,800 Flexible Budget Planning Budget Cars washed Revenue $ 43,080 $ (40) U Expenses: Cleaning supplies Electricity Maintenance...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Results Spending Variances Budget...

  • A complete flexible budget performance report: Multiple Choice would be the same as a planning budget...

    A complete flexible budget performance report: Multiple Choice would be the same as a planning budget report. 0 must be prepared prior to the beginning of the period covered. must be prepared in accordance with GAAP. O would be based on actual activity for the period covered.

  • Exercise 9-14 Prepare a Flexible Budget Performance Report [LO9-4] Lavage Rapide is a Canadian company that owns and op...

    Exercise 9-14 Prepare a Flexible Budget Performance Report [LO9-4] Lavage Rapide is a Canadian company that owns and operates a large automatic car wash facility near Montreal. The following table provides data concerning the company's costs: Fixed Cost Cost per Car Washed $0.60 $e.08 se.30 $0.20 per Month Cleaning supplies Electricity Maintenance $1, 20e Wages and salaries Depreciation Rent $4,50e $8, 200 $1,80e $1,40e Administrative expenses s8.81 For example, electricity costs are $1,200 per month plus $0.08 per car washed....

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Spending Variances Flexible Results Spending Variances Budget 9,520 Activity Variances Planning Budget 9,040 Labor-hours...

  • Please help with below. Thank you! Exercise 9-4 Prepare a Flexible Budget Performance Report [LO9-4] Vulcan...

    Please help with below. Thank you! Exercise 9-4 Prepare a Flexible Budget Performance Report [LO9-4] Vulcan Flyovers offers scenic overflights of Mount St. Helens, the volcano in Washington State that explosively erupted in 1982. Data concerning the company's operations in July appear below: Vulcan Flyovers Operating Data For the Month Ended July 31 Flexible Planning Budget 61 Actual Results Budget Flights (a) 61 59 Revenue ($355.eeq) Expenses: Wages and salaries ($3,400 + $90.00q) Fuel ($33.00) Airport fees ($850 +$32.00q) Aircraft...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Spending Variances Results Budget...

  • Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate...

    Ray Company provided the following excerpts from its Production Department's flexible budget performance report. (Round "rate per hour" answers to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) Required: Complete the Production Department's Flexible Budget Performance Report. Ray Company Production Department Flexible Budget Performance Report For the Month Ended August 31 Actual Flexible Spending Variances Results Budget...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT