The first two answers are correct. Providing the answer for the MRP
10 units of A required in week 6. Lead time is 1 week. So order release of 10 in week 5.
A should start work in week 5. So D and F have requirement of 30 and 20 respectively in week 5.
D has a lead time of 1 week. So order release of 30 in week 4
F has a lead time of 2 weeks. So order release of 20 in week 3.
********
IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!
IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!
Sign Save Homework: Chapter 14 Material Requirements Planning erations Score: 0 of 1 pt 15 of...
Homework: Chapter 14 Material Requirements Planning 11 of 20 (10 complete) HW Score: 42.75%, 8.55 of 20 pl Score: 0 of 1 pt Question Help Problem 14.6 - Bookmatch The demand for subassembly S is 100 units in week 7. Each unit of Srequires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W. and 1 unit of X. Finally, each unit of U requires 2 units of...
Homework: Chapter 14 Material Requirements Planning Save Score: 0 of 1 pt 2 of 20 (1 complete) HW Score: 5%, 1 of 20 pts Problem 14.1 - Bookmatch Question Help You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the...
You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...
Homework: Chapter 7 Supplement Save Score: 0 of 1 pt 1 of 7 (0 complete) HW Score: 0%, 0 of 7 p Problem S7.1 - Bookmatch Question Help Amy Xia's plant is designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day because of the time needed to change equipment between styles of hammers. The utilization rate for the plant -% (enter your answer as a percentage rounded to two decimal places).
have to minimize the cost than $1050
CHAPTER 14 MATERIAL ... 14.18 Develop a lot-for-lot solution and calculate total relevant costs for the data in the preceding table. CHAPTER 14 MATERIAL ... 14.18 Develop a lot-for-lot solution and calculate total relevant costs for the data in the preceding table. se 12 fo he datam the prece in Develop costs for the De our answers for the 19, and 14.20 LEAD 14.18, 14.10 de Koster, or Rene M. de ka ywn...
Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine...
Save Homework: Chapter 5 Homework Score: 0 of 1 pt 6 of 15 (5 complete) HW Score: 20%, 3 of 15 pts X Exercise 8 Question Help As the owner of a family farm whose wealth is $300,000, you must choose between sitting this season out and investing $200,000 in a safe money market fund paying 7 percent option 1) or planting summer com (option 2). Planting costs $200,000, with a six-month time to harvest. If there is rain, planting...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
Homework: Week 4 - Chapter 06 problems Save Score: 0 of 1 pt 4 of 6 (0 complete) HW Score: 0%, 0 of 6 p P6-32A (similar to) Question Help Tomorrows Electronic Center began July with 90 units of merchandise inventory that cost $60 each. During July, the store made the following purchases: EEB (Click the icon to view the purchases.) Tomorrows uses the periodic inventory system, and the physical count at July 31 indicates that 140 units of merchandise...
Analytics Exercise 9-1
Recently, Phil Harris, the production control manager at
Brunswick, read an article on time-phased requirements planning. He
was curious about how this technique might work in scheduling
Brunswick's engine assembly operations and decided to prepare an
example to illustrate the use of time phased requirements
planning.
Phil's first step was to prepare a
master schedule for one of the engine types produced by Brunswick:
the Model 1000 engine. This schedule indicates the number of units
of the...