Question

Homework: Chapter 14 Material Requirements Planning 11 of 20 (10 complete) HW Score: 42.75%, 8.55 of 20 pl Score: 0 of 1 pt Q

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Item : S

Lead Time : 2 weeks

Week ->

1

2

3

4

5

6

7

Gross Requirement

0

0

0

0

0

0

100

Order Release

0

0

0

0

100

0

0

Here, we have a gross requirement of 100 item S in week 7. So gross requirement in other weeks will be 0 and in 7 will be 100.

As lead time is 2 weeks, so the order release will be 100 in week 5 and 0 in other weeks.

********

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!

Add a comment
Know the answer?
Add Answer to:
Homework: Chapter 14 Material Requirements Planning 11 of 20 (10 complete) HW Score: 42.75%, 8.55 of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sign Save Homework: Chapter 14 Material Requirements Planning erations Score: 0 of 1 pt 15 of...

    Sign Save Homework: Chapter 14 Material Requirements Planning erations Score: 0 of 1 pt 15 of 20 (10 complete) HW Score: 42.75%, 8.55 of 20 pts Problem 14.20 - Bookmatch Question Help You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F...

  • solved item S, T, U, V, W, X, Y, Z The demand for subassembly S is...

    solved item S, T, U, V, W, X, Y, Z The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S,...

  • The demand for subassembly S is 120 units in week 7. Each unit of S requires...

    The demand for subassembly S is 120 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W. and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S. 1 week to make T. 2 weeks to make U....

  • Homework: Chapter 14 Material Requirements Planning Save Score: 0 of 1 pt 2 of 20 (1...

    Homework: Chapter 14 Material Requirements Planning Save Score: 0 of 1 pt 2 of 20 (1 complete) HW Score: 5%, 1 of 20 pts Problem 14.1 - Bookmatch Question Help You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the...

  • The demand for subassembly S is 80 units in week 7. Each unit of S requires...

    The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...

  • Problem 14.9 The demand for subassembly S is 120 units in week 7, Each unit of S requires 2 units of T and 1 unit of U....

    Problem 14.9 The demand for subassembly S is 120 units in week 7, Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z One firm manufactures all items. It takes 2 weeks to make S. 1 week to make T, 2 weeks to...

  • You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units...

    You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements...

    Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine...

  • Score: Vot 9 pts 11 of 15 (10 complete) HW Score: 62.9 * More Info follows:...

    Score: Vot 9 pts 11 of 15 (10 complete) HW Score: 62.9 * More Info follows: z Dec. 1 Beginning merchandise inventory 8 Sale 14 Purchase 12 9 units @ $ 10 each units @ $ 24 each units @ $ 15 each units @ $ 24 each 103 21 Sale 13 Inventory on Hand Unit Total Cost Cost Print Done uantity Dec. 1 Dec. 8 Dec. 14 Dec. 21 Totals Enter any number in the edit fields and then...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT