The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T reqProblem 14.6 Question Help The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 1 unsolved item S, T, U, V, W, X, Y, Z

0 0
Add a comment Improve this question Transcribed image text
Answer #1
A gross Requirement Plan showing gross requirements and order release date.
Weeks
  Items Period          1          2          3          4          5          6          7 Lead Time
S Gross requirements 0 0 0 0 0 0 100 2 weeks
Order release 0 0 0 0 100 0 0
T Gross requirements 0 0 0 0 200 0 0 1 weeks
Order release 0 0 0 200 0 0 0
U Gross requirements 0 0 0 0 100 0 0 2 weeks
Order release 0 0 100 0 0 0 0
V Gross requirements 0 0 0 200 0 0 0 2 weeks
Order release 0 200 0 0 0 0 0
W Gross requirements 0 0 0 400 0 0 0 3 weeks
Order release 400 0 0 0 0 0 0
X Gross requirements 0 0 0 200 0 0 0 2 weeks
Order release 0 200 0 0 0 0 0
Y Gross requirements 0 0 100 0 0 0 0 2 weeks
Order release 100 0 0 0 0 0 0
Z Gross requirements 0 0 200 0 0 0 0 1 weeks
Order release 0 200 0 0 0 0 0

Explanation:

Gross requirement of T and U will be at the time of order release of S as they are subparts of S

Gross requirement of V, W & X will be at the time of order release of T as they are subparts of T

Gross requirement of Y & Z will be at the time of order release of U as they are subparts of U

Gross requirement of T will be two times of the order release of S as it requires 2 parts to make one S. Gross requirement of U will be equal to the order release of S as it requires 1 parts to make one S

Gross requirement of V and X will be equal to the order release of T as it requires 1 part to make one T. Gross requirement of W will be two times of the order release of T as it requires 2 parts to make one T

Gross requirement of Y will be equal to the order release of U as it requires 1 part to make one U and Gross requirement of Z will be two times of the order release of U as it requires 2 parts to make one U

С D E F G H Weeks 1 2 3 4 5 6 7 Lead Time 0 0 0 0 0 0 100 0 0 0 0 0 0 2 weeks =14 =G5*2 0 0 0 0 0 0 0 0 lo =G6 0 0 0 1 weeks

Add a comment
Know the answer?
Add Answer to:
solved item S, T, U, V, W, X, Y, Z The demand for subassembly S is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT