1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
S | GR | 120 | ||||||
OH | 20 | |||||||
NR | 100 | |||||||
ORpt | 100 | |||||||
OR | 100 | |||||||
T | GR | 240 | ||||||
OH | 20 | |||||||
NR | 220 | |||||||
ORpt | 220 | |||||||
OR | 220 | |||||||
U | GR | 120 | ||||||
OH | 40 | |||||||
NR | 80 | |||||||
ORpt | 80 | |||||||
OR | 80 | |||||||
V | GR | 240 | ||||||
OH | 20 | |||||||
NR | 220 | |||||||
ORpt | 220 | |||||||
OR | 220 | |||||||
W | GR | 240 | ||||||
OH | 30 | |||||||
NR | 210 | |||||||
ORpt | 210 | |||||||
OR | 210 | |||||||
X | GR | 240 | ||||||
OH | 30 | |||||||
NR | 210 | |||||||
ORpt | 210 | |||||||
OR | 210 | |||||||
Y | GR | 120 | ||||||
OH | 60 | |||||||
NR | 60 | |||||||
ORpt | 60 | |||||||
OR | 60 | |||||||
Z | GR | 240 | ||||||
OH | 40 | |||||||
NR | 200 | |||||||
ORpt | 200 | |||||||
OR | 200 |
For filling this table, we have to use the given data.
The gross requirement is calculated as the total requirement. By taking into consideration the number of units required.
On-hand inventory is the stock that we already have. This is given in a table.
Net requirements are calculated by deducting on-hand inventory from gross requirements.
The order receipt is how much we will recieve. that is same as Net requirements
The order release refers to when to place the order for it getting delivered according to our requirement. We use lead time here.
The demand for subassembly S is 120 units in week 7. Each unit of S requires...
The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...
Problem 14.9 The demand for subassembly S is 120 units in week 7, Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z One firm manufactures all items. It takes 2 weeks to make S. 1 week to make T, 2 weeks to...
solved item S, T, U, V, W, X, Y, Z The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S,...
Homework: Chapter 14 Material Requirements Planning 11 of 20 (10 complete) HW Score: 42.75%, 8.55 of 20 pl Score: 0 of 1 pt Question Help Problem 14.6 - Bookmatch The demand for subassembly S is 100 units in week 7. Each unit of Srequires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W. and 1 unit of X. Finally, each unit of U requires 2 units of...
You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...
Consider the following information about an end-product item: Ordering cost =$45/order Average usage =12 units/week Inventory carrying cost =$1/unit/week (a) How many orders should we place per year (52 weeks) to replenish inventory of the item based on average weekly demand? (b) Given the following time-phased net requirements from an MRP record for this item, determine the sequence of planned orders using economic order quantity (EOQ) and periodic order quantity (POQ) procedures. Assume lead time equals zero and current on-hand...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Beginning inventory L4L 3 weeks 0 150 (week 2) 125 D FOQ = 800 3 weeks 0 300 (week 2) 0 Item E FOQ = 600 4 weeks 0 600 (week 1) 255 L4L 2 weeks 70 None 670 L4L 1 week 0 1,200 (week 1) 0 Print Done Done nd then click Check Answer. Clear All The BOM...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
Lead tmes for purchase or fabrication of each unit to final assembly are Z takes two weeks A, B, C, and D take one week each; and E takes three weeks Fifty units of Product Z ane required in Perod 10 (Assume that there is ourrently no inventory on hand of any of these tems) T 2 Q-LAL Planned order eips Planned order lse LT