Question

Consider the following information about an end-product item: Ordering cost =$45/order Average usage =12 units/week Inventory...

Consider the following information about an end-product item:

Ordering cost =$45/order

Average usage =12 units/week

Inventory carrying cost =$1/unit/week

(a) How many orders should we place per year (52 weeks) to replenish inventory of the item based on average weekly demand?

(b) Given the following time-phased net requirements from an MRP record for this item, determine the sequence of planned orders using economic order quantity (EOQ) and periodic order quantity (POQ) procedures. Assume lead time equals zero and current on-hand inventory equals zero. Calculate the inventory carrying cost on the basis of weekly ending inventory values. Which procedure produces the lowest total cost for the eight-week period?

Week

1

2

3

4

5

6

7

8

Requirements

15

2

10

12

6

0

14

9

0 0
Add a comment Improve this question Transcribed image text
Answer #1

STEP 1: The material Requirement planning (MRP) estimates the amount of material and components required to manufacture a Proyear to replenish Calculate the number of orders per the inventory using following formula Number ol Orders peut year. AveragIf the ending inventory of Preceding weer exceeds the requirement of a week, then the Order quantity needs to be placed in t23 33 BEDE Ele le - Week T I 2 3 4 5 6 7 8 3 Requirements 15 2 110 112 60 149 4 Order quantity 5 Beginning Inventory 16 6 EndSTEP 7 Periodic order Calculate the time between orders in quantity using the following formula - © Time between Ordens - EcoSTEP 8: To Week G 6 15 27 ~ 12 10 8 6 3 Requirements 4 Order quantity 127 Beginning Inventory 6 Ending Inventory 7 Total orde

Add a comment
Know the answer?
Add Answer to:
Consider the following information about an end-product item: Ordering cost =$45/order Average usage =12 units/week Inventory...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1 - the annual demand for product 15600 units the weekly demand is 280 units with...

    1 - the annual demand for product 15600 units the weekly demand is 280 units with a standard deviation 90 units the cost to place an order is $31.00 and the time from order to receipt is 4 weeks the annual inventory carrying cost is $0.10 per unit A- what is the EOQ quantity? B- from the information above what is the reorder point maintain a 95% service level? 2 - the weekly demand is 200 units the cost to...

  • 12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 It...

    12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 Item X L4L On Hand 80 Lead Time 4 70 120 85 50 70 100 Gross Requirements Scheduled Receipts On Hand Net Requirements) Planned Order Receipt Planned Order Release Styles Paragraph tem A 150 FOQ+ 30 On Hand Lead Time 8 5 2 Gross...

  • The following is a partial MRP table. Based on the information provided, an inventory holding cost...

    The following is a partial MRP table. Based on the information provided, an inventory holding cost of $0.39 per unit per week and a setup cost of $139 per order, what would be the planned order release for week 2 using a part period balancing lot sizing approach? Week Gross Requirements Scheduled Receipts On-Hand Inventory Net Requirements Time Phased Net Requirements Planned Order Releases 0 1 2 3 4 5 10 30 20 15 20 40 L | 10 40...

  • sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...

    sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...

  • 5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1...

    5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1 2 3 4 Gross requirements Scheduled receipts Projected ending inventory: 1,000 Net requirements Planned receipts Planned orders Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level...

  • 1.1 ADR Ltd purchases a particular item in lots of 1 250 units. Its annual usage...

    1.1 ADR Ltd purchases a particular item in lots of 1 250 units. Its annual usage of this item is 6 250 units. Ordering costs are R200 per order and the carrying (holding) costs are R10 per unit per year. Calculate each of the following: 1.1.1 The Economic Order Quantity (EOQ) in units 1.1.2 Number of orders 1.1.3 Cost of orders (Order costs) 1.1.4 Average inventory held 1.1.5 Cost of holding stock (3) 1.1.5 Total cost 1.2 Study the extract...

  • Eagle Insurance is a large insurance company chain with a central inventory operation. The company’s fastest-moving...

    Eagle Insurance is a large insurance company chain with a central inventory operation. The company’s fastest-moving inventory item has a demand of 80,000 units per year. The cost of each unit is $200, and the inventory carrying cost is $15 per unit per year. The average ordering cost is $60 per order. It takes about 2 days for an order to arrive. This is a corporate operation, and there are 250 working days per year. (Please show all work including...

  • b)what is the average inventory if the EOQ is used?... units (round your response to two...

    b)what is the average inventory if the EOQ is used?... units (round your response to two decimals) c) what is the optimal number of orders per year?... orders (round your response to two decimals) d) what is the optimal number of days in between any two orders?... days (round your response to two decimals) e) what is the annual cost of ordering and holding inventory? ...$per year (round your response to two decimals) f)what is the total annual inventory cost,...

  • Data Table Annual demand for denim cloth 40,700 yards Ordering cost per purchase order $185 Carrying...

    Data Table Annual demand for denim cloth 40,700 yards Ordering cost per purchase order $185 Carrying cost per year 10% of purchase costs Safety-stock requirements None Cost of denim cloth $11 per yard The purchasing lead time is 2 weeks. The Fabric World is open 220 days a year (44 weeks for 5 days a week). The Fabric World sells fabrics to a wide range of industrial and consumer users. One of the products it carries is denim cloth, used...

  • 1. Which of the following affects the calculation of the reorder point? a. Average usage b....

    1. Which of the following affects the calculation of the reorder point? a. Average usage b. Average lead time c. Safety stock d. All of the above 2. The role of safety stock in an organization is to a. Reduce the lead-time for an order to be received. b. Reduce the likelihood of a stockout. c. Reduce the reorder point. d. Decrease the economic order quantity. 3. The costs of preparing, issuing, and paying purchase orders, plus receiving and inspecting...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT