MRP for System Unit, Speakers and CD-ROM Drivers is as below:
SYSTEM UNIT | Lead Time | 1 week | Minimum order qty | 14500 | ||
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Gross requirements | 11000 | 4000 | 4000 | 4000 | 4500 | |
Scheduled receipts | ||||||
Projected ending inventory: 7500 | 7500 | 14500+7500-11000=11000 | 11000-4000=7000 | 7000-4000=3000 | 14500+3000-4500=13000 | 13000-4500=8500 |
Net requirements | 11000-7500=3500 | 4000-3000=1000 | ||||
Planned receipts | 14500 | 14500 | ||||
Planned orders | 14500 | 14500 | ||||
SPEAKERS | Lead Time | 1 week | Minimum order qty | 11000 | ||
For every 1 unit of System unit, 2 units of Speakers are required | ||||||
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Gross requirements | 14500*2=29000 | 14500*2=29000 | ||||
Scheduled receipts | 2500 | |||||
Projected ending inventory: 17500 | 0 | 11000+17500+2500-29000=2000 | 2000 | 27000+2000-29000=0 | 0 | 0 |
Net requirements | 29000-17500-2500=9000 | 29000-2000=27000 | ||||
Planned receipts | 11000 | 27000 | ||||
Planned orders | 11000 | 27000 | ||||
CD-ROM Drivers | Lead Time | 1 | Minimum order qty | 15500 | ||
For every 1 unit of System unit, 1 unit of CD-Rom Driver is required | ||||||
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Gross requirements | 14500 | 14500 | ||||
Scheduled receipts | ||||||
Projected ending inventory: 1000 | 0 | 1000+15500-14500=2000 | 2000 | 2000+15500-14500=3000 | 3000 | 3000 |
Net requirements | 14500-1000=13500 | 14500-2000=12500 | ||||
Planned receipts | 15500 | 15500 | ||||
Planned orders | 15500 | 15500 |
Please give thumbs up/ likes if you consider my answer useful.
Thank you!
5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1...
Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 8,000 kits in week 2 Start assembling 2,500 kits in weeks 3,...
Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross Requirements Scheduled receipts Projected ending Inventory Net Requirements Planned Receipts Planned Orders 400 500 300 0 C 100 100 300 OA 200 O B. 400 O C. 500 O D. 300 8a Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross...
calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...
Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases
Given the following (incomplete) MRP record: Oats Lead Time = 2 weeks Week 1 Week 2 Week 3 Week 4 Week 5 Gross Requirements (lb) 12814 24323 24872 18464 17938 Scheduled Receipts 44000 Planned Receipts On Hand 23635 Planned Orders What is the On Hand number in week 1?
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...
Problem 14-5 To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.) One unit of A is made of three units of B, one unit of C, and...
Please answer the following question for week #2: This is from page 495 of Managing Operations Across the Supply Chain by author Morgan Swink 3. Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On hand = 30 Safety stock = 20 Order quantity: FOQ = 100 Week Week Week Week Week Week Week Week 2 Gross Requirements 7050 7060 80 Scheduled Receipts Available Inventory Net Requirements Planned Order Receipts Planned...
Case #2 MGT2315 There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of...