Question

Given the following (incomplete) MRP record: Oats     Lead Time = 2 weeks Week 1 Week 2...

Given the following (incomplete) MRP record:

Oats     Lead Time = 2 weeks

Week 1

Week 2

Week 3

Week 4

Week 5

Gross Requirements (lb)

12814

24323

24872

18464

17938

Scheduled Receipts

44000

Planned Receipts

On Hand

23635

Planned Orders

What is the On Hand number in week 1?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Book1 Excel Sign in HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Cut Copy FILE 2 AutoSum A Fill Gerneral libri ConditionBook1 Excel Sign in HOME INSERT PAGE LAYOUT FORMULAS DATA REVIEW VIEW Cut Copy ,Format Painter , FILE Σ AutoSum . A Gerneral

Week-1 On hand= 10821

Please comment if any doubt

Rate me

Thanks

Add a comment
Know the answer?
Add Answer to:
Given the following (incomplete) MRP record: Oats     Lead Time = 2 weeks Week 1 Week 2...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using this MRP record and a lead time of 3 weeks, what should the planned orders...

    Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross Requirements Scheduled receipts Projected ending Inventory Net Requirements Planned Receipts Planned Orders 400 500 300 0 C 100 100 300 OA 200 O B. 400 O C. 500 O D. 300 8a Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross...

  • Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time =...

    Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases

  • calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled...

    calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...

  • 5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1...

    5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1 2 3 4 Gross requirements Scheduled receipts Projected ending inventory: 1,000 Net requirements Planned receipts Planned orders Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level...

  • Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using...

    Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using a L4L lot-sizing strategy. Repeat using a fixed order quantity of 106 frames. Compare and contrast the results. What are the benefits and drawbacks to each approach? (Leave no cells blank - be certain to enter "O" wherever required.) picture Click here for the Excel Data File Part Name: Bicycle frame Week 6 Week 5 Week 7 Week 8 Week 1 Week 3 Week...

  • Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a...

    Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 8,000 kits in week 2 Start assembling 2,500 kits in weeks 3,...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT