Question

Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross Requirements Sched
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: Option D (300)

Assume that it is pre decided about the project on hand after week 3, it will be auto directed to planned orders and will be 500-200 = 300.

Please leave a like. Thanks a lot.

Add a comment
Know the answer?
Add Answer to:
Using this MRP record and a lead time of 3 weeks, what should the planned orders...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled...

    calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...

  • Given the following (incomplete) MRP record: Oats     Lead Time = 2 weeks Week 1 Week 2...

    Given the following (incomplete) MRP record: Oats     Lead Time = 2 weeks Week 1 Week 2 Week 3 Week 4 Week 5 Gross Requirements (lb) 12814 24323 24872 18464 17938 Scheduled Receipts 44000 Planned Receipts On Hand 23635 Planned Orders What is the On Hand number in week 1?

  • Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time =...

    Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases

  • 5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1...

    5 6 CD-ROM drivers: Lead Time = 1 week: Minimum order quantity = 15,500 Week 1 2 3 4 Gross requirements Scheduled receipts Projected ending inventory: 1,000 Net requirements Planned receipts Planned orders Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level...

  • Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a...

    Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level O kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 8,000 kits in week 2 Start assembling 2,500 kits in weeks 3,...

  • For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in...

    For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19?     For the Office Table above, what are the Planned Order Receipts in the week of 8/8?     For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19?     For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5?    We were unable to transcribe this imageMS.53 An office...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • Given the data provided for product structure, component AC101, and the planned orders of parent AB...

    Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...

  • Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using...

    Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using a L4L lot-sizing strategy. Repeat using a fixed order quantity of 106 frames. Compare and contrast the results. What are the benefits and drawbacks to each approach? (Leave no cells blank - be certain to enter "O" wherever required.) picture Click here for the Excel Data File Part Name: Bicycle frame Week 6 Week 5 Week 7 Week 8 Week 1 Week 3 Week...

  • * 0. THE CAR FRAMEWOR X Walmart of-Topic KX C In The Following MRP PLEX ments/210071...

    * 0. THE CAR FRAMEWOR X Walmart of-Topic KX C In The Following MRP PLEX ments/210071 by 4:59pm Points 10 Submitting an external tool Available until Jun 7 In the following requirements schedule, X is equal to 1 3 N 250 250 125 Week Gross Requirements Scheduled Receipts Available Inventory Net Requirements Planned Order Receipt Planned Order Release 180 X 125 125 a. O b. 125 O C. 180 d. 305 If there is a planned order release of 120...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT