Question

Please answer the following question for week #2: This is from page 495 of

Managing Operations Across the Supply Chain by author Morgan Swink

3. Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On hand = 30 Safety stock = 20 O

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

As per the given problem, following information/constraints are identified for managing Operations Across the Supply Chain of Part : Seat

  • Lead Time = 1 week
  • On hand = 30
  • Safety Stock = 20
  • Order quantity = 100

Thus, it is evident that no new order can be given, unless inventory level goes below 20. That’s the minimum inventory level has to be maintained.

Based on the above, set of information, the MRP record is constructed below:

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Gross Requirements

70

50

70

80

70

60

60

80

Scheduled Receipts

30

60

110

40

60

90

30

70

Available Inventory

30

60

110

40

60

90

30

70

Net Requirements

40

-10

-40

40

10

-30

30

10

Planned Order Receipts

100

100

-

100

100

-

100

Planned Order Release

100

100

100

100

100

The net requirement indicates shortage of supply. If it is negative, then it indicates over supply in that specific week. If over supply is less than 20, then new order is released. The units of new order released, are received in the next week as the lead-time is 1 week.

Therefore, in 8 week time span, total five times new order has to be released (last week is not considered as requirement for subsequent weeks are not available).

The answer for week 2 is also covered in the above table, which is again given below:

Week 2

Gross Requirements

50

Scheduled Receipts

60

Available Inventory

60

Net Requirements

-10

Planned Order Receipts

100

Planned Order Release

100


Add a comment
Know the answer?
Add Answer to:
Please answer the following question for week #2: This is from page 495 of Managing Operations...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time =...

    Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases

  • Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using...

    Please show all work. Thanks in advance Complete the MRP record for a bicycle frame using a L4L lot-sizing strategy. Repeat using a fixed order quantity of 106 frames. Compare and contrast the results. What are the benefits and drawbacks to each approach? (Leave no cells blank - be certain to enter "O" wherever required.) picture Click here for the Excel Data File Part Name: Bicycle frame Week 6 Week 5 Week 7 Week 8 Week 1 Week 3 Week...

  • supply chain question, please solve it anyone.

    There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of its assemblies/components Part 1:...

  • Given the data provided for product structure, component AC101, and the planned orders of parent AB...

    Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...

  • Given the following (incomplete) MRP record: Oats     Lead Time = 2 weeks Week 1 Week 2...

    Given the following (incomplete) MRP record: Oats     Lead Time = 2 weeks Week 1 Week 2 Week 3 Week 4 Week 5 Gross Requirements (lb) 12814 24323 24872 18464 17938 Scheduled Receipts 44000 Planned Receipts On Hand 23635 Planned Orders What is the On Hand number in week 1?

  • 12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 It...

    12. (25 points) Complete the MRP calculations for the simple product shown below. Numbers next to each item identify the usage rates. For example, the usage rate for item A is 2. A2 C3 C2 B1 Item X L4L On Hand 80 Lead Time 4 70 120 85 50 70 100 Gross Requirements Scheduled Receipts On Hand Net Requirements) Planned Order Receipt Planned Order Release Styles Paragraph tem A 150 FOQ+ 30 On Hand Lead Time 8 5 2 Gross...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • provide step by step explanation of calculation. thanks

    Case #2 MGT2315  There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...

  • Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct...

    Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT