1)
Projects should be accepted if the return > Cost of capital (ie WACC). In the above example, as a has an average risk (ie WACC = 8%) and return (11%) > WACC, a should be accepted. All other projects have WACC > Return.
Answer is A)
2)
Cumulative cash flows in year 1 = -500 + 150 = -350
Cumulative cash flows in Year 2 = -350 + 200 = -150
Cumulative cash flows in Year 3 = -150 + 600 = 450
Regular payback = 2 + (150/600) = 2.25 years
Answer is C) 2.25 years
Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...
LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 9%. B) Accept Project b, if Project b is...
LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%, which of the following projects (A, B, and C) should the company accept? O A. Project B, which is of below-average risk and has a return of 8.5%. O B. None of the projects listed in the choices should be accepted. C. Project C, which is of above-average risk...
Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk projects. Which of the following independent projects should the company accept? Assume the company uses NPV as its primary accept/reject criteria and that all projects have conventional cash flows. a. Without information about the projects' NPVs, we cannot determine which projects should be accepted. b. Project A, which has average risk and an IRR = 9%. c. All of the projects...
Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the followingindependent projects should Tapley accept, assuming that the company uses the NPV method when choosing projects?a.Project A, which has average risk and an IRR = 9%.b.Project B, which has below-average risk and an IRR = 8.5%.c.Project C, which has above-average risk and an IRR = 11%.d.Without information about the projects' NPVs we cannot determine which...
Hampton Manufacturing estimates that its WACC is 12%. The company is considering the following seven investment projects: Project Size IRR $650,000 13.6% 13.1 В 1,050,000 12,5 1,050,000 C D. 1,200,000 12.3 600,000 E 12.2 F 600,000 11.6 650,000 11.5 a. Assume that each of these projects is independent and that each is just as risky as the firm's existing assets. Which set of projects should be accepted? -Select Project A -Select Project B -Select Project C Project D -Select Project...
Problem 10-18 WACC and optimal capital budget Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return $2,000 16.00% 3,000 15.00 5,000 13.75 2,000 12.50 The company estimates that it can issue debt at a rate of ra = 9%, and its tax rate is 30%. It can issue preferred stock that pays a constant dividend of $6 per year at $40 per share. Also, its common stock currently...
Problem 10-18 WACC and optimal capital budget Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return 16.00% $2,000 3,000 15.00 5,000 13.75 2,000 12.50 The company estimates that it can issue debt at a rate of r-9%, and its tax rate is 40%. It can issue preferred stock that pays a constant dividend of $6 per year at $59 per share. Also, its common stock currently sells for...
Problem 10-18 WACC and optimal capital budget Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return $2,000 1 16.00% 2 3,000 15.00 3 5,000 13.75 12.50 4 2,000 The company estimates that it can issue debt at a rate of rd10 % , and its tax rate is 30 %. It can issue preferred stock that pays a constant dividend of $4 per year at $49 per share....
y: WACC and optimal capital budget Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return $2.000 16.00% 3,000 15.00 13.75 5,000 2,000 12.50 The company estimates that it can issue debt at a rate ofre=11%, and its tax rate is 40%. It can issue preferred stock that pays a constant dividend of $6 per year at $56 per share. Also, its common stock currently sells for $31 per...
WACC and optimal capital budget Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Project Cost Expected Rate of Return $2,000 16.00% 3,000 15.00 5,000 13.75 2,000 12.50 The company estimates that it can issue debt at a rate ofre -10%, and its tax rate is 30%. It can issue preferred stock that pays a constant dividend of $4 per year at $42 per share. Also, its common stock currently sells for $37 per...