Question

Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for av...continues

Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the followingindependent projects should Tapley accept, assuming that the company uses the NPV method when choosing projects?a.Project A, which has average risk and an IRR = 9%.b.Project B, which has below-average risk and an IRR = 8.5%.c.Project C, which has above-average risk and an IRR = 11%.d.Without information about the projects' NPVs we cannot determine which one or ones should be accepted.e.All of these projects should be accepted.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
for independent projects the only requirement to get accepted is that req rate of return < IRR....the only one which meets this condition is project B(the below avg risk project)
answered by: Billie Jo
Add a comment
Answer #2
The answer is B


Hope this helps
answered by: life-line
Add a comment
Know the answer?
Add Answer to:
Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for av...continues
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk proje...

    Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk projects. Which of the following independent projects should the company accept? Assume the company uses NPV as its primary accept/reject criteria and that all projects have conventional cash flows. a. Without information about the projects' NPVs, we cannot determine which projects should be accepted. b. Project A, which has average risk and an IRR = 9%. c. All of the projects...

  • LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 9%. B) Accept Project b, if Project b is...

  • LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%, which of the following projects (A, B, and C) should the company accept? O A. Project B, which is of below-average risk and has a return of 8.5%. O B. None of the projects listed in the choices should be accepted. C. Project C, which is of above-average risk...

  • Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk project: have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 11%. B) Accept Project b, if Project b is...

  • Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to...

    Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to accept or reject will always be the same using either the MIRR method or the NPV method. b. The IRR method is appealing to some managers because it produces a rate of return upon which to base decisions rather than a dollar amount like the NPV method. c. One of the disadvantages of choosing between mutually exclusive projects on the basis of discounted payback...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...

  • Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...

  • Purple Whale Foodstuffs Inc. is evaluating a proposed capital budgeting project (project Sigma) that will require...

    Purple Whale Foodstuffs Inc. is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. Purple Whale Foodstuffs Inc. has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because returns in percentage form are easier to understand and compare to required returns. Purple Whale Foodstuffs Inc.'s WACC is...

  • Don't need explanations, just comparing my answers. Thank you. Suppose Green Caterpillar Garden Supplies Inc. is...

    Don't need explanations, just comparing my answers. Thank you. Suppose Green Caterpillar Garden Supplies Inc. is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $450,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $375,000 Year 2 $425,000 Year 3 $400,000 Year 4 $450,000 Green Caterpillar Garden Supplies Inc.'s weighted average cost of capital is 10%, and project Alpha has the same risk as the firm's...

  • 6. Within-firm risk and beta risk Understanding risks that affect projects and the impact of risk...

    6. Within-firm risk and beta risk Understanding risks that affect projects and the impact of risk consideration WSP Inc. is involved in a wide range of unrelated projects. The company will pursue any project that it thinks will create value for its stockholders. Consequently, the risk level of the company's projects tends to vary a great deal from project to project If WSP Inc. does not risk-adjust its discount rate for specific projects properly, which of the following is likely...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT