Question

Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk proje...

Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk projects. Which of the following independent projects should the company accept? Assume the company uses NPV as its primary accept/reject criteria and that all projects have conventional cash flows.

a.

Without information about the projects' NPVs, we cannot determine which projects should be accepted.

b.

Project A, which has average risk and an IRR = 9%.

c.

All of the projects should be accepted as they would produce a positive NPV.

d.

Project C, which has above-average risk and an IRR = 11%.

e.

Project B, which has below-average risk and an IRR = 8.5%.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Without information about the projects' NPVs, we cannot determine which projects should be accepted.

As company's criterion for decision is NPV, so decision cannot be made based on IRR method.

Add a comment
Know the answer?
Add Answer to:
Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk proje...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for av...continues

    Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the followingindependent projects should Tapley accept, assuming that the company uses the NPV method when choosing projects?a.Project A, which has average risk and an IRR = 9%.b.Project B, which has below-average risk and an IRR = 8.5%.c.Project C, which has above-average risk and an IRR = 11%.d.Without information about the projects' NPVs we cannot determine which...

  • LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 9%. B) Accept Project b, if Project b is...

  • LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%, which of the following projects (A, B, and C) should the company accept? O A. Project B, which is of below-average risk and has a return of 8.5%. O B. None of the projects listed in the choices should be accepted. C. Project C, which is of above-average risk...

  • Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk project: have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 11%. B) Accept Project b, if Project b is...

  • Considering the following two projects, if the WACC =10%, then I should: Project Year 0 1...

    Considering the following two projects, if the WACC =10%, then I should: Project Year 0 1 2 3 4 A Cash flows -$100 $50 $60 $70 $80 B Cash flows -$100 $50 $50 $50 $50 Accept project A since its NPV = $102.27 is higher than project B’s NPV = $58.49 Accept project B since its NPV = $102.27 is higher than project A’s NPV = $58.49 Project A’s NPV = - $102.27. Thus, I shall reject project A and...

  • Hampton Manufacturing estimates that its WACC is 12%. The company is considering the following seven investment...

    Hampton Manufacturing estimates that its WACC is 12%. The company is considering the following seven investment projects: Project Size IRR $650,000 13.6% 13.1 В 1,050,000 12,5 1,050,000 C D. 1,200,000 12.3 600,000 E 12.2 F 600,000 11.6 650,000 11.5 a. Assume that each of these projects is independent and that each is just as risky as the firm's existing assets. Which set of projects should be accepted? -Select Project A -Select Project B -Select Project C Project D -Select Project...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...

  • 1) if a company uses its WACC as the discount rate for all of the projects...

    1) if a company uses its WACC as the discount rate for all of the projects it undertakes then the company will tend to: A) reject all high-risk projects B) accept all positive net present value projects C) increase the average risk level of the company over time D) favor low-risk projects over high-risk projects F) reject all negative net present value projects 2)Which one of the following is an example of unsystematic risk? A) Decrease in the national level...

  • CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

    CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...

  • 11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this...

    11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:    0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT