Question

0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 Lecture Exercise #14 0.0 0.1 0.2 0.3 0.4 .5120 5517 .5910 .6293 .6664 .7019

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Based on the given data, we find the expected duration and variance for each activity as shown below:

Variance Activity Optimistic Most Likely Pessimistic Activity Predecessor m b Expected duration a + 4m + b 6 10 o² = (a - by?

Based on the above expected duration, we prepare a project entowrk diagram as shown below:

1596163973239_image.png

The above network diagram in form of formulas is shown below for better understanding and reference

A с D E F G H K 1 B Legend ID EFT N 3 4 EST SLK LST DUR LFT B =E4+F6 5 =C6 =E6-E4 =G6-F6 12 =18 60 A=A6+B8 7 =A8-A6 8 =C8-B8

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly, LFT & LST are calculated during the backward pass.

There are 2 paths in the diagram. However, path A-B-D is the longest path and has 0 slack. Hence, this is the critical path of the project.

As seen from the network diagram, the expected project completion time = 30 days

The variance of project completion time = Sum of Variances over critical path = Variance for activity A + Variance for Activity B + Variance for activity D = 0.11 + 4 + 1 = 5.11

Std. Deviation of project completion time = \sigma =  \sqrt{Variance} = \sqrt{5.11} = 2.261

We find the probability of completion in 33 days or less as shown below:

R = 33 days

E = 30 days

Z value = \frac{R-E}{\sigma } = \frac{33-30}{2.261} = 1.33

For Z = 1.33, Probability from Z table chart = 0.9082 = 90.82%

We find the probability of completion in 28 days or less as shown below:

R = 28 days

E = 30 days

Z value = \frac{R-E}{\sigma } = \frac{28-30}{2.261} = (-0.89)

For Z = (-0.89), Probability from Z table chart = (1 - Probability for Z=0.89) = (1 - 0.8133) = 0.1867 = 18.67%

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!

Add a comment
Know the answer?
Add Answer to:
0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 Lecture Exercise #14 0.0 0.1 0.2...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish...

    Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path . Activity А Time (days) 6 7 3 Predecessor(s) None None B с A 2 A E 4 B F 6 B 10 C. E D. F H 7 Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 2 1 А B None None None с 1 1 Cost Normal Crash 1000...

  • CUMULATIVE PROBABILITIES FOR THE STANDARD NORMAL DISTRIBUTION (Continued) TABLE 1 Cumulative probability Entries in the table...

    CUMULATIVE PROBABILITIES FOR THE STANDARD NORMAL DISTRIBUTION (Continued) TABLE 1 Cumulative probability Entries in the table give the area under the curve to the left of the z value. For example, for 2- 1.25, the cumulative probability is 8944 Ζ.00.01 .02 .03 .04 .05 .06 .07 .08 .09 0 5000 5040 5080 5120 5160 5199 5239 5279 5319 5359 1 5398 5438 5478 5517 5557 5596 5636 5675 5714 5753 2 5793 5832 5871 .5910 5948 .5987 .6026 .6064 .6103...

  • Use the standard normal table to find the specified area. 0 Area under a normal curve...

    Use the standard normal table to find the specified area. 0 Area under a normal curve to the left of 2 (page 2) To the right of z=0.11 Click here to view page 1 of the standard normal table, Click here to view page 2 of the standard normal table The area to the right of z=0.11 is 0.4562 (Round to four decimal places as needed. .7088 Table of Areas to the Left of: When : Is Positive 2 .00...

  • Save Check My Work to (to 4 decimals) b. what is the probability that the sample...

    Save Check My Work to (to 4 decimals) b. what is the probability that the sample proportion will be within ±0.03 of the population proportion. Round your answer to four decimals. will be within 0.05 of the population proportion, Round your answer to four decimals. r answer-3. This is because the increase in the sample size makes the standard error, op.-Select your answer Check My Work TABLE CUMULATIVE PROBABILITTES FOR THE STANDARD TORMAL DISTRIBUTION (Continued) prcbhabilby Eatris n tte give...

  • Q Search this course Homework of 70 n ±8 of the population mean (to 4 decimals)?...

    Q Search this course Homework of 70 n ±8 of the population mean (to 4 decimals)? Check TABLE 1 CUMULATIVE PROBABILITIES FOR THE STANDARD NORMAL DISTRIBUTION (Continued) probability Entries in the table give the area under the curve to the left of the z valuc. For example, for z-1.25, the cumulative probability is 8944 0 5000 5040 5080 5120 5160 5199 5239 52795319 5359 1 5398 5438 5478 5517 55575596 5636 5675 5714 5753 2 5793 5832 5871 5910 59485987...

  • A population proportion is 0.5. A sample of size 150 will be taken and the sample...

    A population proportion is 0.5. A sample of size 150 will be taken and the sample proportion p will be used to estimate the population proportion. Use z-table Round your answers to four decimal places. a. what is the probability that the sample proportion will be within ±0.03 of the population proportion? b, what is the probability that the sample proportion will be within ±0.08 ofthe population proportion? president of D erm an Distributors, Inc., beleves that 32% of the...

  • Assume that adults have IQ scores that are normally distributed with a mean of μ=100 and...

    Assume that adults have IQ scores that are normally distributed with a mean of μ=100 and a standard deviation σ=20. Find the probability that a randomly selected adult has an IQ less than 132. Positive z Scores                                       Standard Normal (z) Distribution: Cumulative Area from the Left                                       z    .00    .01    .02    .03    .04    .05    .06   ...

  • Let X be a normal random variable with mean 4 and variance 9. Use the normal...

    Let X be a normal random variable with mean 4 and variance 9. Use the normal table to find the following probabilities, to an accuracy of 4 decimal places. Normal Table The entries in this table provide the numerical values of Φ(z)=P(Z≤z), where Z is a standard normal random variable, for z between 0 and 3.49.For example, to find Φ(1.71), we look at the row corresponding to 1.7 and the column corresponding to 0.01, so that Φ(1.71)=.9564. When z is...

  • A survey found that women's heights are normally distributed with mean 63.7 in and standard deviation...

    A survey found that women's heights are normally distributed with mean 63.7 in and standard deviation 2.3 in. A branch of the military requires women's heights to be between 58 in and 80 in. a. Find the percentage of women meeting the height requirement. Are many women being denied the opportunity to join this branch of the military because they are too short or too tall? b. If this branch of the military changes the height requirements so that all...

  • eBook Video A population has a mean of 300 and a standard deviation of 80. Suppose...

    eBook Video A population has a mean of 300 and a standard deviation of 80. Suppose a sample of size 125 is selected and X is used to estimate μ. Use z-table. a. What is the probablity that the sample mean will be within+3 of the population mean (to 4 decimals)? (Round z value in intermediate calculations to 2 decimal places) b. What is the probability that the sample mean will be within+/- 19 of the population mean (to 4...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT