Question

. The operation manager of a body and paint shop has five cars to schedule for...

. The operation manager of a body and paint shop has five cars to schedule for repair. He would like to minimize throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are listed below.

(a) Determine the job sequence using the Johnson rule.

(b) How much idle time is related to painting? (use a chart to find out the idle time for painting).

car Body work hrs paint hrs
A 12 6
B 7 4
C 9 10
D 3 4
E 12 5
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Using Johnsons Rule as: (in select the job with the mininum processing time (either in operation 1 or 2) (1) It the minimumSequence a) Job D 2 c 3 A s E 5 B b) Cantt chart is shown below: 0 3 12 24 36 43 с А Body work B A mully Paint EL А C B 7 12

Add a comment
Know the answer?
Add Answer to:
. The operation manager of a body and paint shop has five cars to schedule for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. The operation manager of a body and paint shop has five cars to schedule for...

    3. The operation manager of a body and paint shop has five cars to schedule for repair. He would like to minimize throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are listed below. Car Body Work (Hours) Paint (Hours) JA 12 B 17 6 14 10 C 19 D 3 E 12 4 5 (a) Determine...

  • 3. The operation manager of a body and paint shop has five cars to schedule for...

    3. The operation manager of a body and paint shop has five cars to schedule for repair. He would like to minimize throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are listed below. Car А B с D E Body Work (Hours) 12 7 9 3 12 Paint (Hours) 6 4 10 4 5 (a) Determine...

  • 3. The operation manager of a body and paint shop has five cars to schedule for...

    3. The operation manager of a body and paint shop has five cars to schedule for repair. He would like to minimize throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are listed below. Paint (Hours) 6 Car A B C D E Body Work (Hours) 12 7 9 4 10 4 3 12 in (a) Determine...

  • QUESTION 5 Ricardo Gonzalez is now helping his brother who works at a body and paint...

    QUESTION 5 Ricardo Gonzalez is now helping his brother who works at a body and paint shop. The shop has five cars to schedule for repair. They would like to minimize throughput time to complete all work on these cars.  Each car requires body work prior to painting.  The estimates of the time required to do the body and paint work on each area are as follows: CAR BODY WORK (hours) PAINT (hours) A 37 21 B 21 17 C 14 16...

  • The manager of a car garage must schedule repairs on five (5) cars. he would like to minimize the...

    The manager of a car garage must schedule repairs on five (5) cars. he would like to minimize the total processing time of the five cars. Repairs on each car require two successive activities: sheet metal and painting. The relevant data for the five cars are given in the following table Cars Sheet metal (hours) Painting (hours) v1 8 7 v2 9 4 v3 7 9 v4 3 4 v5 12 5 a) Use Johnson's rule to determine the optimal...

  • (a) Allan's job shop takes order for making spare parts for textile manufacturing equipment. The operation...

    (a) Allan's job shop takes order for making spare parts for textile manufacturing equipment. The operation milling and involves first milling and then finishing. Table Q4(a) presents the data of processing times for each job. (i) Determine the sequencing rule using First Come First Serve (FCFS) and Johnson's Rule. (4 marks) (ii) Make a work schedule on a Gantt chart using FCFS rules indicating the makespan. (6 marks) (iii) Make a work schedule on a Gantt chart using Johnson's rules...

  • QUESTION TWO A. Fiifi Auto mobile company manufactures cars and trucks. Each vehicle must be processed...

    QUESTION TWO A. Fiifi Auto mobile company manufactures cars and trucks. Each vehicle must be processed in the paint shop and body assembly shop. If the paint shop were only painting trucks, then 80 per day could be painted. If the paint shop were only painting cars, then 120 per day could be painted. If the body shop were only producing cars, then it could process 100 per day. If the body shop were only producing trucks, then it could...

  • Operations Scheduling. You are a manager of an injection molding shop, and need to schedule several...

    Operations Scheduling. You are a manager of an injection molding shop, and need to schedule several jobs on your largest molding machine. You decide to restrict the order of your choices somewhat to take an advantage of subsequent processing that some jobs must undergo. There are six jobs to be scheduled on the molding machine. Job 1 should be done before job 4 and job 3 before job 5. Processing times, due dates (both in days) and the cost (as...

  • Roberts Auto Sales and Service (RASAS) consists of three car dealerships that sell and service several...

    Roberts Auto Sales and Service (RASAS) consists of three car dealerships that sell and service several makes of American and Japanese cars, two auto parts stores, a large body shop and car painting business, and an auto salvage yard. Vicky Roberts, owner of RASAS, went into the car business when she inherited a Ford dealership from her father. She was able to capitalize on her knowledge and experience to build her business into the diversified and successful mini-empire it is...

  • Ashley Oakley was hired by the Battleground Nurseries (BN), a commercial nursery and landscape supply company...

    Ashley Oakley was hired by the Battleground Nurseries (BN), a commercial nursery and landscape supply company in Oak Ridge, NC, as an Analyst in their newly-formed Project Office (PO). She reported to work and was assigned a small cubicle with an old laptop computer. Not what she had hoped for in her first job, but she was grateful to land her first job in a rapidly growing economy and resolved to give it her best effort. The PO reported to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT