Question 3 A firm wants to develop a level material use schedule based on the following data. What should be the setup cost?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: 66.248

Explanation:

Desired Lot Size (Q) = 728 units

Annual Demand (D) = 40000 units per year

Holding Cost (H) = $20 units per year

Daily Production Rate (p) = 320 units per day

Daily Demand (d) = 40000/250 = 160 units per day

Setup Cost = S

Q = \sqrt{\frac{2*S*D}{H*(1-d/p)}}

Q^2 = (2*S*D)/(H*(1-d/p))

728^2 = (2*S*40000)/(20*(1-160/320))

S = $66.248

Add a comment
Know the answer?
Add Answer to:
Question 3 A firm wants to develop a level material use schedule based on the following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 33 A firm wants to develop a level material use schedule based on the following...

    Question 33 A firm wants to develop a level material use schedule based on the following data. What should be the setup cost? Desired lot size Annual Demand Holding Cost Daily production rate Working days per year Excel Access 728 units 40,000 units per year $20 per unit per year 320 units per day 250 days per year

  • Question 16 A firm wants to develop a level material use schedule based on the following...

    Question 16 A firm wants to develop a level material use schedule based on the following data. What should be the setup cost? Desired lot size Annual Demand Holding Cost Daily production rate Working days per year Excel Access 628 units 40,000 units per year $20 per unit per year 320 units per day 250 days per year

  • A firm wants to develop a level material use schedule based on the following data. What...

    A firm wants to develop a level material use schedule based on the following data. What should be the setup cost? Desired lot size Annual Demand Holding Cost Daily production rate Working days per year Excel Access 815 units 40,000 units per year $20 per unit per year 320 units per day 250 days per year

  • 3. A repetitive manufacturing firm is planning on level material use. The following information has been...

    3. A repetitive manufacturing firm is planning on level material use. The following information has been collected. Currently, the firm operates 250 days per year. Annual demand (D) 20,000 Daily demand (d) Daily production (p) 250 Desired lot size (Q) Holding cost per unit per year (H) $50 1) What is the setup cost based on the desired lot size? (10 points) 80 2) What is the desired setup time based on $50 hour setup labor? (10 points) 3) Theoretically,...

  • Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to...

    Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses a work year of 290 days. Setup labor cost ​$40.00 per hour Annual holding cost ​$16 per unit Daily production​ (8 hours) 960 units/day Annual demand for steering wheels 29,000 ​(290 days×daily demand of 100 ​units) Desired lot size​ (2 hours of​ production) Q= 240 units A) what is the setup cost? B) what is...

  • Given the following information about a product, at Phyllis Simon's firm, what is the appropriate setup...

    Given the following information about a product, at Phyllis Simon's firm, what is the appropriate setup time? Setup labor cost $50.00 per hour Annual holding cost $13 per unit Daily production1,200 units/day Annual demand 43,500 (290 days each x daily demand of 150 units) Desired lot size 150 units Setup timeminutes (round your response to two decimal places)

  • Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to...

    Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses year of 290 days. Setup labor cost $40.00 per hour Annual holding cost $15 per unit Daily production (8 hours) 800 units/day Annual demand for steering wheels 34,800 (290 days x daily demand of 120 units) Desired lot size (2 hours of production) Q = 200 units a) Setup cost = $ (round your response...

  • Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to...

    Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses a work year of 290 days. Setup labor cost Annual holding cost $60.00 per hour $13 per unit 960 units/day Daily production (8 hours) Annual demand for steering wheels 31,900 (290 days x daily demand of 110 units) Desired lot size (2 hours of production) Q 240 units a) Setup cost = $ (round your...

  • a) Setup Cost: b) Setup Time: Rick Wing has a repetitive manufacturing plant producing automobile steering...

    a) Setup Cost: b) Setup Time: Rick Wing has a repetitive manufacturing plant producing automobile steering wheels. Use the following data to prepare for a reduced lot size. The firm uses a work year of 305 days. Setup labor cost $40.00 per hour Annual holding cost $16 per unit Daily production (8 hours) 800 units day Annual demand for steering wheels 36,600 (305 days x daily demand of 120 units) Desired lot size (2 hours of production) 0 - 200...

  • Homework: HW-CH16 Score: 0 of 1 pt Problem 16.2 2 of 4 (1 complete) Given the...

    Homework: HW-CH16 Score: 0 of 1 pt Problem 16.2 2 of 4 (1 complete) Given the following information about a product, at Michael Gibson's firm, what is the appropriate setup time? Setup labor cost$30.00 per hour Annual holding cost $29 per unit Daily production Annual demand Desired lot size 1,200 units/day 42,000 (280 days each xdaily demand of 150 units) 300 units Setup time-□ minutes (round your response to two decimal places).

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT